9510
Comment:
|
11504
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/13 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180313.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/17(Tue.) === | |
Line 51: | Line 52: |
2017/3/20(Tue.) * Remote participants by eZuce: None |
* Remote participants by eZuce: None |
Line 56: | Line 55: |
* VAC: *Kimura * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks. |
|
Line 57: | Line 58: |
* VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. |
* ETMX: *Hasegawa * Damping for yaw woks somehow and RMS is ~0.2urad. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY: :Miyamoto, Shishido * No progress for damping. * ETMY: *Okutomi * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
Line 60: | Line 66: |
* Alignment: *Izumi * All alignment to REFL after pump down was verified. |
* DGS: *Yamamoto * IO chassis of k1ioo was disconnected somehow. |
Line 64: | Line 70: |
* ETMY: *Miyamoto | |
Line 69: | Line 74: |
* Alignment, ETMY: *Izumi | * IFO: Enomoto, Nakano * Damping, BS L2P, restoring alignment. |
Line 71: | Line 77: |
* Cal: * Calibration test using MC is planned tomorrow. |
* VAC: *Kimura * Identifies the location of leak. * VAC: *Inoue * Vacuum gage for wide area will be installed. |
Line 76: | Line 85: |
* [AM] IR: all, Green: off. * [PM] IR: all, Green: off. * [night] IR: all, Green: off |
* [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 82: | Line 99: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 88: | Line 104: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
* week of 4/23 * Operation |
Line 92: | Line 107: |
* Issues | ==== Issues ==== * Large leak was found but it is not identified where it is. * IO chassis of k1ioo was disconnected somehow. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
Line 105: | Line 125: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
|
Line 131: | Line 155: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/17(Tue.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Kimura
- Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
- ETMX: *Hasegawa
- Damping for yaw woks somehow and RMS is ~0.2urad.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY: :Miyamoto, Shishido
- No progress for damping.
- ETMY: *Okutomi
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
- DGS: *Yamamoto
- IO chassis of k1ioo was disconnected somehow.
Work plan (*:responsible person)
- IFO: Enomoto, Nakano
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Identifies the location of leak.
- VAC: *Inoue
- Vacuum gage for wide area will be installed.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
- Large leak was found but it is not identified where it is.
- IO chassis of k1ioo was disconnected somehow.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools