Line 11: | Line 11: |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/5(Thur.) === | |
Line 51: | Line 52: |
2017/3/21(Thur.) * Remote participants by eZuce: Kimura, Miyoki |
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa |
Line 56: | Line 55: |
* Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. |
|
Line 57: | Line 60: |
* IFO: *Izumi, Miyamoto, Eleonora * Daily Beam check was confirmed at the REFL port yesterday evening. * Measurement of BS sensing and driving matrix and diagonalizarion of them. * This method should be automatically performed, but still we needs some work to be done. * T of ETMY was checked and improved. We need the same work for L. * LSC screen has been updated. |
* ETMX: *Ushiba * Circuits and connection are still being checked. |
Line 64: | Line 63: |
* AOS: *Akutsu, Yokogawa * Green light reached to ETMY on Tuesday. Misalignment was ~100urad order. |
* Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. |
Line 67: | Line 67: |
* DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. |
|
Line 68: | Line 72: |
* IMC, CAL: Yokozawa, Yamamoto * IMC Transmitted light is too low. Alignment should be checked. * Injection to MCE for calibration was tested. * VAC: Uchiyama * Vacuum level of X arm is degraded. |
* Vacuum: *Kimura * Closing door will be performed in the next week. |
Line 75: | Line 75: |
* PCal: no one to report * TMS: no one to report |
|
Line 77: | Line 80: |
* Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. |
|
Line 78: | Line 83: |
* Alignment: *Izumi * ETMY control, BS diagonalizatiom, Checking baffle PD of ETMX. * Needs power supply for QPD. |
* ETMY: *Miyamoto * Cover on Oplev will be set this morning. |
Line 82: | Line 86: |
* AOS: *Akutsu, Yokogawa * TMS alignment at ETMY. * Cooling will start at 10AM. |
* DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
Line 88: | Line 91: |
* [AM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [PM] IR: Upstream SR2-3 line, Yend 1F. Green: Around PR2, Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 94: | Line 105: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
Line 100: | Line 110: |
* week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
Line 104: | Line 114: |
* Issues | ==== Issues ==== |
Line 117: | Line 128: |
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/5(Thur.)
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa
Report of work (*:responsible person)
- Alignment: Izumi
- Both light had been confirmed at REFL yesterday morning.
- IR beam was lost at REFL evening, but green was still seen.
- Both IR and green were still seen at Y end.
- ETMX: *Ushiba
- Circuits and connection are still being checked.
- Dolphin: *Yamamoto
- Connected IMC, IOO and BS.
- Error indicator is seen on BS.
- DAQ: *Yamamoto
- Memory will be increased today. SSD might be tested today at k1tw0.
- Data stream of ITMX and SR3 are stopped for a while until the end of phase 1.
- k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many.
- Vacuum: *Kimura
- Closing door will be performed in the next week.
- PCal: no one to report
- TMS: no one to report
Work plan (*:responsible person)
- Alignment: Izumi
- IR will be re-aligned this morning. It requires green off evening.
- ETMY: *Miyamoto
- Cover on Oplev will be set this morning.
- DAQ: *Miyakawa
- Memory will be increased today. SSD might be tested today at k1tw0.
Laser hazard
* [AM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
* [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- 4/5 12:30 at fan hut: Meeting before pump down 1
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)