Line 11: | Line 11: |
2017/3/20 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180320.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/27(Fri.) === | |
Line 51: | Line 41: |
2017/3/23(Fri.) * Remote participants by eZuce: Izumi, Miyoki |
* Remote participants by eZuce: None |
Line 57: | Line 45: |
* IFO: *Izumi, Miyamoto, Eleonora * BS had some difficulty to close control loop of Y of oplev. * T of ETMY control loop was closed. * Circuits of baffle PD are being prepared. |
* IFO: *Izumi, Enomoto + many * Michelson lock lasted longer than 2 and half hours! * Alignment control from IFO to ETMX was implemented by dithering ETMX. * RT models for PR2 and PR3 were down sampled from 16kHz to 2kHz. (Ushiba) * PR3 alignment was implemented by baffle signal. * ETMX damping might be a cause of lock lost. * ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba) * BS oplev is fed back to not only TM but also IM. (Arai) |
Line 62: | Line 54: |
* AOS: *Akutsu, Yokogawa * Green team succeeded to reach green and IR to ETMY. * BRT alignment is going on yesterday and today. * Oplev is being prepared at EXC. |
* WAB: *Akutsu * Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater. * Equilibrium temperature was 21K. * Damping became to strong in low temperature. |
Line 67: | Line 59: |
* Camera: Yokozawa, Yamamoto, Miyamoto * X end camera will be recovered. * IYC cooling started. |
* SR: *Mark, Enzo, Tanioka, Kozu * Wire of RM was broken on SR3 during tightening clamp. There was no damage. |
Line 71: | Line 62: |
* CAL: *Yamamoto * Line injection is being tested. * UGF serve will not be implemented, so change of optical gain is compensated in off line. * Operaton: * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] is opened. * Operation schedule and emergency contact list is put on the white board in the control room. |
|
Line 74: | Line 72: |
* Alignment: *Eleonora, Miyamoto * BS diagonalization * ETMY damping * AOS: *Akutsu, Yokogawa * BRT alignment is going on yesterday and today. * Oplev work at EXC. |
* IFO: *Izumi, Enomoto, Nakano + many * Measurement without locking morning, measurement with locking in the afternoon. |
Line 85: | Line 78: |
* IR: PSL * Green: around PR2 |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 88: | Line 81: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 92: | Line 85: |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F. * Green: Xend 1F. |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 97: | Line 91: |
* week of 3/19 * TMS alignment using green light at ETMY. * 3/21~: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa |
* week of 4/23 * Michelson control. * 4/28 Operation start |
Line 103: | Line 95: |
* week of 3/26 * Rough alignment of ETMX is planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. |
==== Issues ==== |
Line 107: | Line 97: |
* Issues | |
Line 120: | Line 109: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || ||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || ||24||2018/3/27||[[KAGRA/Commissioning/Weekly/20180327/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180327.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180327/Minute|Minute]]|| || |
|
Line 146: | Line 139: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/27(Fri.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- Michelson lock lasted longer than 2 and half hours!
- Alignment control from IFO to ETMX was implemented by dithering ETMX.
- RT models for PR2 and PR3 were down sampled from 16kHz to 2kHz. (Ushiba)
- PR3 alignment was implemented by baffle signal.
- ETMX damping might be a cause of lock lost.
- ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
- BS oplev is fed back to not only TM but also IM. (Arai)
- WAB: *Akutsu
- Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
- Equilibrium temperature was 21K.
- Damping became to strong in low temperature.
- SR: *Mark, Enzo, Tanioka, Kozu
- Wire of RM was broken on SR3 during tightening clamp. There was no damage.
- CAL: *Yamamoto
- Line injection is being tested.
- UGF serve will not be implemented, so change of optical gain is compensated in off line.
- Operaton:
Operation wiki page is opened.
- Operation schedule and emergency contact list is put on the white board in the control room.
Work plan (*:responsible person)
- IFO: *Izumi, Enomoto, Nakano + many
- Measurement without locking morning, measurement with locking in the afternoon.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)