Line 50: | Line 50: |
=== 2018/4/9(Mon.) === | |
Line 51: | Line 52: |
2017/3/28(Wed.) * Remote participants by eZuce: None |
* Remote participants by eZuce: |
Line 56: | Line 55: |
* IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto * Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX. * Connection between k1lsc and k1bs was done. |
|
Line 57: | Line 59: |
* Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto * Height was adjusted, and started yaw alignment. GAS filter had a sudden jump, and it is being fixed today. * First contact will be removed. * BS: *Enomoto * DAC had some glitches with no output (even dac kill and master SW are off). * It will be investigated more. |
|
Line 64: | Line 60: |
* BRT: Akutsu * Worked well, it means beam spot can be controllable. * Beam shape looks elliptic a bit. |
* DAQ: *Miyakawa * Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well. |
Line 70: | Line 65: |
* Alignment: Enomoto * Alignment to ETMX will be verified Tuesday evening. |
|
Line 71: | Line 68: |
* Vacuum: Kimura * Disassembling outer frames today * Closing will be done tomorrow. * Installation of Illuminator and viewport are still remaining. It will be done today. * Laser will be stopped day time during this week. |
|
Line 74: | Line 76: |
* IR: PSL, Pend 1F * Green: PR2 |
* IR: PSL, Yend 1F * Green: off |
Line 77: | Line 79: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 81: | Line 83: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 86: | Line 89: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
|
Line 87: | Line 93: |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa |
==== Issues ==== |
Line 93: | Line 95: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * week of 4/9 * Issues |
|
Line 113: | Line 107: |
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || | |
Line 140: | Line 135: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/9(Mon.)
* Remote participants by eZuce:
Report of work (*:responsible person)
- IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
- Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX.
- Connection between k1lsc and k1bs was done.
- DAQ: *Miyakawa
- Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well.
Work plan (*:responsible person)
- Alignment: Enomoto
- Alignment to ETMX will be verified Tuesday evening.
- Vacuum: Kimura
- Disassembling outer frames today
- Closing will be done tomorrow.
- Installation of Illuminator and viewport are still remaining. It will be done today.
- Laser will be stopped day time during this week.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: PSL, Yend 1F
- Green: off
- [night]
- IR: PSL, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)