2018/4/2(Fri.) | === 2018/4/9(Mon.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Enomoto | * Remote participants by eZuce: |
Line 55: | Line 55: |
* ETMX: *Ushiba * Confirmed the returned beam at REFL * Calibration of OpLev is on going (mostly finished) * Start Characterization |
* IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto * Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX. * Connection between k1lsc and k1bs was done. |
Line 60: | Line 59: |
* ETMY: *Miyamoto * Damping is working well. Less than 2urad RMS. |
|
Line 63: | Line 60: |
* BS: *Enomoto * Two different problems identified * Apparent bi-stability of OpLev -> Replaced the satellite box -> Gone * Glitches -> Looks like the same problem as ETMY: DAC output goes to zero |
* DAQ: *Miyakawa * Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well. |
Line 68: | Line 63: |
* PCal: Binhua * Aligned the beam within the PCal module * ETMX camera: Yokozawa * Ready but not installed * TMS: no one to report |
|
Line 77: | Line 65: |
* Alignment: Enomoto * Alignment to ETMX will be verified Tuesday evening. |
|
Line 78: | Line 68: |
* ETMX: *Ushiba, Miyamoto * Start Characterization * BS: Enomoto * Check the glitches over the weekend * PCal: Binhua * Measure PCal transfer functions * ETMX Camera: Yokozawa * Set up necessary components to take high frame rate pictures ==== Laser hazard ==== * [AM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F 2017/3/30(Fri.) * Remote participants by eZuce: None ==== Report of work (*:responsible person) ==== * ETMX: *Takahashi, Ishizaki, Sato, Okutomi, Tomaru, Takahashi, Ushiba, Miyamoto, Enomoto, Nagano * Mirror will be aligned with beam today to REFL. But IR and green are not overlapped well. * Oplev is placed but not calibrated. * LVDT of BF seems to be something wrong. It could be satellite box. * BS: *Enomoto, Enzo * Hightower coil driver and satellite box was replaced. Satellite box was something wrong. Oplev jump disappeared. But still glitch remains. * Hyper threading should be off. * BRT: Nagano * TMS was seen and aligned to QPD. * ==== Work plan (*:responsible person) ==== * ETMX: *Ushiba, Takahashi * Beam will be aligned more precisely with aligned IR. * CAL: *Yamamoto * CAL model is tested using iMC. * Camera: Yokozawa * EX camera takes every one hour. It is necessary 1 sec picture in the weekend. |
* Vacuum: Kimura * Disassembling outer frames today * Closing will be done tomorrow. * Installation of Illuminator and viewport are still remaining. It will be done today. * Laser will be stopped day time during this week. |
Line 138: | Line 76: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 141: | Line 79: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 145: | Line 83: |
* IR: SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
* IR: PSL, Yend 1F * Green: off |
Line 150: | Line 89: |
* week of 3/26 * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Connection of cable at ETMX and starting control. * Rough alignment of ETMX using IR. * 3/27 EX PD will be removed.: *Yokozawa * week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. |
|
Line 161: | Line 90: |
* 4/11 12:30 at fan hut: Meeting before pump down 2 | |
Line 165: | Line 95: |
* BS: DAC had some glitches but if DAC is off, no glitch was found. | |
Line 178: | Line 107: |
||25||2018/4/3||[[KAGRA/Commissioning/Weekly/20180403/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180403.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180403/Minute|Minute]]|| || | |
Line 205: | Line 135: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/3/26 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/9(Mon.)
* Remote participants by eZuce:
Report of work (*:responsible person)
- IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto
- Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX.
- Connection between k1lsc and k1bs was done.
- DAQ: *Miyakawa
- Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well.
Work plan (*:responsible person)
- Alignment: Enomoto
- Alignment to ETMX will be verified Tuesday evening.
- Vacuum: Kimura
- Disassembling outer frames today
- Closing will be done tomorrow.
- Installation of Illuminator and viewport are still remaining. It will be done today.
- Laser will be stopped day time during this week.
Laser hazard
- [AM]
- IR: PSL, Yend 1F
- Green: off
- [PM]
- IR: PSL, Yend 1F
- Green: off
- [night]
- IR: PSL, Yend 1F
- Green: off
Weekly
- week of 4/9
- 4/11 12:30 at fan hut: Meeting before pump down 2
- Closing EXC
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)