== Current task == | == Working people assignment == . * 責任者 * ビーム位置測定 * 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC * 11/1 *内山、寺田、木村、沢田@EXA . * 11/5 *内山、寺田、木村、井上、沢田@EYA * 11/6 *内山、寺田、木村、井上、沢田@IYA * 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木 . * 11/8 *木村、荒木、沢田@IXV, IXC、荒木 * 11/9 *木村、荒木、沢田@IYV, IYC、荒木 |
Line 6: | Line 18: |
----- ----- == Meetings == |
|
Line 7: | Line 23: |
== Meeting == === Weekly meeting === * Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokum Kaikan, or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for phase1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| |
|
Line 26: | Line 29: |
2017/10/10(Mon) | 2017/10/30(Mon) |
Line 29: | Line 32: |
* 作業人員 * MIF: 苔山、横澤、新井、三代、和泉、中野、榎本 * Laser hazard: 川村 * 午前に各種準備で、午後からハザードエリア。 * 午後1時から2時まで見学があるので、午後3時頃からハザートエリア。 * 確認事項 * PRMは固定で進める、準備完了。 * k1pr0のIOシャーシを交換したので、問題があったら報告。 * PR2リモートテストも完了。順調。 * BS: あと少し。キャリブレーションなど。 * 先週の報告通りチェンバー中心からずれているが、そのまま進める。今日IMMT2でアラインメントをする。 * Gマット張り完了。 * BSの出口は塞いだままアラインメントを進める。 |
* 作業人員(*:責任者) * 位置測定: *内山、寺田、木村、井上、沢田@IXA, IXC(PHS: V-10寺田、V-9井上) * VIS: Mark, Enzo, 神津 * ビーム調整: 中野、三代 * Laser hazard * PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。 * ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。 * Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。 * 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。 * 作業 * アラインメント * ビーム位置測定 * IXAのタンクのベローズを外して、フランジ面を出し、IXA側にスクリーンを置きビームを見た。その位置でビームを床に落とす。ビームがダクト中心に対して53mmだけ-Y側、+13mm上側にずれていた。 * その時ゲートバルブのビューポートを見たら、IXAからゲートバルブを見て右上側(-Y側)に見えた。 * EXに光を当てた状態で、PR3の真ん中に入れると、フロントのビューポートの真ん中から3-4cmずれる。PDのカウントが11000程度になり、台風前に戻った。理論値は1.4cmだけ-Y側にずれる。 * フロントのビューポートの真ん中に入れると、PR3の真ん中からずれる。ただしクリップはされていない。PDのカウントのほとんど改善はなかった。 * 最後にPR3の真ん中に戻した。 * 今日は@IXA, IXCでビーム位置を落とす。 |
Line 43: | Line 55: |
* 今週の目標はPR3からの光がBSまで届くこと。 * PRとBSの間のダクトをどうするかはクリーンネスの問題から、今日のweekly meetingで検討。 * PR側のアルミは使う人が各自外して使う。 * PR周りの測定をしたい。(大石) -> スケジュールを今日のweekly meetingで検討。 |
* 10/30の週: ビーム位置測定。 |
Line 48: | Line 58: |
* 今日はアラインメントのタスクがMIF担当になっていて、作業する人はアサインされている。問題になったのは、責任者が決まっていなくて、入坑者の把握がまとまってできていない。入坑確認ことなどもあるので、タスク分担の分の現場の責任者を決めて入坑する人の取りまとめをする。 | * コーチフィルターが不調。 * 防振装置の操作の伝授 |
Line 53: | Line 64: |
---- ==== Weekly meeting ==== * Date and time: Every Tuesday, 11AM * Location: Meeting room at Hokum , or educe, Polycom ||No.||Date||Agenda||Minute||Files|| || || || || || || ||7||2017/10/31||[[KAGRA/Commissioning/Weekly/20171031/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171031/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=4|G1707278-v4]]|| ||6||2017/10/24||[[KAGRA/Commissioning/Weekly/20171024/Agenda|Agenda]] ||[[KAGRA/Commissioning/Weekly/20171024/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=3|G1707278-v3]]|| ||5||2017/10/17||[[KAGRA/Commissioning/Weekly/20171017/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171017/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=2|G1707278-v2]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7298|G1707298]]<<BR>>[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7300|G1707300]]|| ||4||2017/10/10|| ||[[KAGRA/Commissioning/Weekly/20171010/Minute|Minute]]||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278&version=1|G1707278-v1]]|| ||3||2017/10/3||[[KAGRA/Commissioning/Weekly/20171003/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20171003/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_20171003.pptx|Commissioning plan for phase1]]|| ||2||2017/9/26||[[KAGRA/Commissioning/Weekly/20170926/Agenda|Agenda]]||[[KAGRA/Commissioning/Weekly/20170926/Minute|Minute]]||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709025.pptx|Commissioning plan for phase1]]|| ||1||2017/9/19|| || ||[[attachment:KAGRA/Commissioning/Commissioning_Phase1_201709012.pptx|Commissioning plan for phase1]]|| ---- === Other meetings === * Meeting about PR2 pitch misalignment ([[KAGRA/Commissioning/DailyWork/2017-10-12/Minute|Minute]]) * [[KAGRA/Commissioning/CommissioningWorkshop2017|Commissioning Workshop 2017]] |
|
Line 55: | Line 84: |
----- | |
Line 57: | Line 86: |
* [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=xxxx|Commissioning plan for Phase1]] | * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7278|Commissioning plan for Phase1]] |
KAGRA Commissioning Wiki
Working people assignment
- * 責任者
- ビーム位置測定
- 10/31 *内山、寺田、木村、井上、沢田@IXC, IYC
- 11/1 *内山、寺田、木村、沢田@EXA
- 11/5 *内山、寺田、木村、井上、沢田@EYA
- 11/6 *内山、寺田、木村、井上、沢田@IYA
- 11/7 *内山、寺田、木村、井上、沢田@予備日、荒木
- 11/8 *木村、荒木、沢田@IXV, IXC、荒木
- 11/9 *木村、荒木、沢田@IYV, IYC、荒木
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or educe
2017/10/30(Mon)
- Daily
- 作業人員(*:責任者)
- 位置測定: *内山、寺田、木村、井上、沢田@IXA, IXC(PHS: V-10寺田、V-9井上)
- VIS: Mark, Enzo, 神津
- ビーム調整: 中野、三代
- Laser hazard
- PSL直後で120mW、IMC出口で100mW程度、PRM以降は10mW程度。
- ハザードエリアはSR2とSR3の間のラインより奥(機械室は除く)。
- Yエンド、Yアームに行く方は、保護メガネを使い中央エリアを通過し、メガネはそのまま持って行って、帰りの中央エリアも保護メガネを使い通過してください。
- 両エンドはハザードエリアではないですが、真空槽まわりで作業する人は保護メガネをかけください。
- 作業
- アラインメント
- ビーム位置測定
- IXAのタンクのベローズを外して、フランジ面を出し、IXA側にスクリーンを置きビームを見た。その位置でビームを床に落とす。ビームがダクト中心に対して53mmだけ-Y側、+13mm上側にずれていた。
- その時ゲートバルブのビューポートを見たら、IXAからゲートバルブを見て右上側(-Y側)に見えた。
- EXに光を当てた状態で、PR3の真ん中に入れると、フロントのビューポートの真ん中から3-4cmずれる。PDのカウントが11000程度になり、台風前に戻った。理論値は1.4cmだけ-Y側にずれる。
- フロントのビューポートの真ん中に入れると、PR3の真ん中からずれる。ただしクリップはされていない。PDのカウントのほとんど改善はなかった。
- 最後にPR3の真ん中に戻した。
- 今日は@IXA, IXCでビーム位置を落とす。
- 作業人員(*:責任者)
- Weekly
- 10/30の週: ビーム位置測定。
- 問題点など
- コーチフィルターが不調。
- 防振装置の操作の伝授
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokum , or educe, Polycom
No. |
Date |
Agenda |
Minute |
Files |
|
|
|
|
|
7 |
2017/10/31 |
|||
6 |
2017/10/24 |
|||
5 |
2017/10/17 |
|||
4 |
2017/10/10 |
|
||
3 |
2017/10/3 |
|||
2 |
2017/9/26 |
|||
1 |
2017/9/19 |
|
|
Other meetings
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools
Issue tracker: Bugzilla (currently site internal only)