10740
Comment:
|
11504
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/5(Thur.) === | === 2018/4/17(Tue.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa | * Remote participants by eZuce: None |
Line 55: | Line 55: |
* Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. |
* VAC: *Kimura * Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks. |
Line 60: | Line 58: |
* ETMX: *Ushiba * Circuits and connection are still being checked. |
* ETMX: *Hasegawa * Damping for yaw woks somehow and RMS is ~0.2urad. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY: :Miyamoto, Shishido * No progress for damping. * ETMY: *Okutomi * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
Line 63: | Line 66: |
* Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. |
* DGS: *Yamamoto * IO chassis of k1ioo was disconnected somehow. |
Line 67: | Line 69: |
* DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. |
|
Line 72: | Line 70: |
* Vacuum: *Kimura * Closing door will be performed in the next week. |
|
Line 75: | Line 71: |
* PCal: no one to report * TMS: no one to report |
|
Line 80: | Line 73: |
* Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. |
|
Line 83: | Line 74: |
* ETMY: *Miyamoto * Cover on Oplev will be set this morning. |
* IFO: Enomoto, Nakano * Damping, BS L2P, restoring alignment. |
Line 86: | Line 77: |
* DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
* VAC: *Kimura * Identifies the location of leak. * VAC: *Inoue * Vacuum gage for wide area will be installed. |
Line 91: | Line 85: |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F |
* [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 94: | Line 88: |
* [PM] * IR: SR2-3 line, Xend 1F, Yend 1F |
* [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 98: | Line 92: |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F |
* [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 105: | Line 99: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 110: | Line 104: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
* week of 4/23 * Operation |
Line 116: | Line 109: |
* Large leak was found but it is not identified where it is. * IO chassis of k1ioo was disconnected somehow. * A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts. * ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock. |
|
Line 128: | Line 125: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || |
|
Line 156: | Line 155: |
* Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter#preview|Check list]]) | * Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at ETMX 1 ([[/Meetings/Others/20180405|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) * Meeting for pump down test at Center are ([[/Meetings/Others/20180314|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumCenter|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/17(Tue.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Kimura
- Large leak was found but it is not identified where it is. Currently Vacuum level is 200Pa, but it should be around 0.1Pa if no leaks.
- ETMX: *Hasegawa
- Damping for yaw woks somehow and RMS is ~0.2urad.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY: :Miyamoto, Shishido
- No progress for damping.
- ETMY: *Okutomi
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
- DGS: *Yamamoto
- IO chassis of k1ioo was disconnected somehow.
Work plan (*:responsible person)
- IFO: Enomoto, Nakano
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Identifies the location of leak.
- VAC: *Inoue
- Vacuum gage for wide area will be installed.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
- Large leak was found but it is not identified where it is.
- IO chassis of k1ioo was disconnected somehow.
- A very high Q peak was found on pitch and it takes several hours to be calm. This high Q seems to be Sphere parts.
- ETMY TF was measured. Not only 2 but all F1, F2, F3 seem to be locked. Moving FR may fix the lock.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools