Line 11: | Line 11: |
2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/5(Thur.) === | === 2018/4/18(Wed.) === |
Line 52: | Line 52: |
* Remote participants by eZuce: Kimura, Miyoki, Yokozawa | * Remote participants by eZuce: None |
Line 55: | Line 55: |
* Alignment: Izumi * Both light had been confirmed at REFL yesterday morning. * IR beam was lost at REFL evening, but green was still seen. * Both IR and green were still seen at Y end. |
|
Line 60: | Line 56: |
* ETMX: *Ushiba * Circuits and connection are still being checked. |
* VAC: *Kimura * One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today. * There are 3 ways to the operation in the newt week; * Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay. * Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days. * Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX. |
Line 63: | Line 63: |
* Dolphin: *Yamamoto * Connected IMC, IOO and BS. * Error indicator is seen on BS. |
* ETMX: *Hasegawa * TF for MM coupling of photo sensor was found. * RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something. |
Line 67: | Line 67: |
* DAQ: *Yamamoto * Memory will be increased today. SSD might be tested today at k1tw0. * Data stream of ITMX and SR3 are stopped for a while until the end of phase 1. * k1script had no remaining resource and was something wrong. Daemon of dbus? was started too many. |
|
Line 72: | Line 68: |
* Vacuum: *Kimura * Closing door will be performed in the next week. |
* ETMY: *Nakano, Shishido * Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad. |
Line 75: | Line 71: |
* PCal: no one to report * TMS: no one to report |
* IFO: *Enomoto, Izumi * Trial lock of Michelson did not succeed because of too much motion of ETMY. * BS: *Eleonora, Izumi * We are optimizing diagonalization of L2P filter. Needs more time. * DGS: *Yamamoto * Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again. |
Line 80: | Line 83: |
* Alignment: Izumi * IR will be re-aligned this morning. It requires green off evening. |
|
Line 83: | Line 84: |
* ETMY: *Miyamoto * Cover on Oplev will be set this morning. |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. |
Line 86: | Line 87: |
* DAQ: *Miyakawa * Memory will be increased today. SSD might be tested today at k1tw0. |
* VAC: *Kimura * Identifies the location of leak. |
Line 91: | Line 92: |
* [AM] * IR: SR2-3 line, Xend 1F, Yend 1F |
* [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 94: | Line 95: |
* [PM] * IR: SR2-3 line, Xend 1F, Yend 1F |
* [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 98: | Line 99: |
* [night] * IR: SR2-3 line, Xend 1F, Yend 1F |
* [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F |
Line 105: | Line 106: |
* week of 4/2 * ETMY damping. * Rough alignment of ETMX using IR, and control MICH if can. * 4/5 12:30 at fan hut: Meeting before pump down 1 |
* week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. |
Line 110: | Line 111: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
* week of 4/23 * Operation |
Line 116: | Line 116: |
* Large leak was found but it is not identified where it is. | |
Line 128: | Line 128: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || |
|
Line 156: | Line 158: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/18(Wed.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- VAC: *Kimura
- One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today.
- There are 3 ways to the operation in the newt week;
Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay.
Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days.
Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX.
- ETMX: *Hasegawa
- TF for MM coupling of photo sensor was found.
- RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something.
- ETMY: *Nakano, Shishido
- Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad.
- IFO: *Enomoto, Izumi
- Trial lock of Michelson did not succeed because of too much motion of ETMY.
- BS: *Eleonora, Izumi
- We are optimizing diagonalization of L2P filter. Needs more time.
- DGS: *Yamamoto
- Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again.
Work plan (*:responsible person)
- IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Identifies the location of leak.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check.
- Opening the last gate valve.
- week of 4/23
- Operation
Issues
- Large leak was found but it is not identified where it is.
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools