2017/3/26 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180327.png||width=1200}} |
2017/5/01 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180501.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/9(Mon.) === | === 2018/5/1(Tue.) === |
Line 52: | Line 41: |
* Remote participants by eZuce: | * Remote participants by eZuce: None * 4th day of Phase 1 operation * TF of ETMX * [[KAGRA/Commissioning/Phase1/Operation|Operation wiki page]] |
Line 55: | Line 48: |
* IFO: Izumi, Enomoto, Nakano, Ushiba, Yamamoto * Light from ETMY was seen at the REFL. No light was confirmed from ETMX due to the work at ETMX. * Connection between k1lsc and k1bs was done. |
* IFO: *Izumi, Enomoto + many * DAC on PR3: Yamamoto * PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause. * lock lost was ~100min, including guardian misrecording. * DAQ was dead 2-3min. * Noise budged: *Tanioka, Izumi, Enomono * PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved. * 100Hz noise seems to be dominated by beam position of BS or ETMY. * TF of BS was well done. * CBC injection was well done. * DGS: *Miyakawa * Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once. ==== Work plan (*:responsible person) ==== * TF of Type A: Okutomi, Miyamoto |
Line 60: | Line 70: |
* DAQ: *Miyakawa * Minute raw date is being shifted to k1tw0. k1fw0 currently writing full and science and minute data seems to be working very well. ==== Work plan (*:responsible person) ==== * Alignment: Enomoto * Alignment to ETMX will be verified Tuesday evening. * Vacuum: Kimura * Disassembling outer frames today * Closing will be done tomorrow. * Installation of Illuminator and viewport are still remaining. It will be done today. * Laser will be stopped day time during this week. |
|
Line 76: | Line 73: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 79: | Line 76: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 83: | Line 80: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 89: | Line 86: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC |
* week of 4/30 * Operation continues. |
Line 107: | Line 103: |
||28||2018/5/1||[[KAGRA/Commissioning/Weekly/20180501/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180501.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180501/Minute|Minute]]|| || ||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || ||26||2018/4/10||[[KAGRA/Commissioning/Weekly/20180410/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180410.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180410/Minute|Minute]]|| || |
|
Line 135: | Line 134: |
* Meeting for pump down test at ETMX 2 ([[/Meetings/Others/20180411|Minute]], [[KAGRA/Commissioning/Phase1/Task/CheckList/20180307_VacuumETMX|Check list]]) |
KAGRA Commissioning Wiki
Task list
Schedule
2017/5/01 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/5/1(Tue.)
* Remote participants by eZuce: None * 4th day of Phase 1 operation
- TF of ETMX
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- DAC on PR3: Yamamoto
- PR3 DAC was dead. Reboot of k1pr3 fixed, but we are not sure the cause.
- lock lost was ~100min, including guardian misrecording.
- DAQ was dead 2-3min.
- Noise budged: *Tanioka, Izumi, Enomono
- PR2 oplev loop was improved, and MICH noise around 10-20Hz was improved.
- 100Hz noise seems to be dominated by beam position of BS or ETMY.
- DAC on PR3: Yamamoto
- TF of BS was well done.
- CBC injection was well done.
- DGS: *Miyakawa
- Timing signal was connected k1iy0 on Sunday, it requires a reboot of RT PC of k1iy0 once.
Work plan (*:responsible person)
- TF of Type A: Okutomi, Miyamoto
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/30
- Operation continues.
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools