10626
Comment:
|
11015
|
Deletions are marked like this. | Additions are marked like this. |
Line 11: | Line 11: |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 24: | Line 24: |
* Laser, Ref''''''Cav, IMC: 苔山、中野 * IMMT: 大石 * VIS * Type Bp: 正田、三代 * Type B: Mark * Type A: 奥富、宮本 * Pico''''''Motor: 三代 * Digital: 山本、宮川 * 回路: 上泉、霜出 * DC電源関連: 宮川 * AC電源関連: 粟井 * 水漏れなど: 古田、早河 |
|
Line 50: | Line 39: |
=== 2018/4/12(Thur.) === | === 2018/4/26(Thur.) === |
Line 55: | Line 44: |
* IFO: Enomoto, Nagano, Nagano * 5 front gate valve opened and beam was verified at the Y end baffle PD. * Beam shift was only ~10urad when the gate valve opened. * One of the monitor of gate valve did not work. * Final check at X end was done. * Coil driver for Marionette was changed from low to high. * Damping of ETMX will be tested with HPCD. |
* IFO: *Izumi, Enomoto + many * Michelson lock lasted longer than 2 and half hours! * Alignment control from IFO to ETMX was implemented by dithering ETMX. * PR3 alignment was implemented by baffle signal. * ETMX damping might be a cause of lock lost. * ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba) * BS oplev is fed back to not only TM but also IM. (Arai) * WAB: *Akutsu * Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater. * Equilibrium temperature was 21K. * Damping became to strong in low temperature. * Wire of RM was broken on SR3 during tightening clamp. * CAL: *Yamamoto * line injection is being tested. |
Line 64: | Line 66: |
* IFO: damping work or others. * VAC: closing ETMX door. * Pumping starts tomorrow morning. |
* IFO: *Izumi, Enomoto, Nakano + many * Measurement without locking morning, measurement with locking in the afternoon. * |
Line 71: | Line 75: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 74: | Line 78: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 78: | Line 82: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 84: | Line 88: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC * Some controls for Michelson * 4/13 moning Pump down * week of 4/16 * Michelson control * Leak check |
|
Line 95: | Line 89: |
* Operation | * Michelson control. * 4/28 Operation start |
Line 99: | Line 94: |
* PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered? * PR3 also had jumps caused by DAC glitches. |
|
Line 111: | Line 108: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/26(Thur.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- IFO: *Izumi, Enomoto + many
- Michelson lock lasted longer than 2 and half hours!
- Alignment control from IFO to ETMX was implemented by dithering ETMX.
- PR3 alignment was implemented by baffle signal.
- ETMX damping might be a cause of lock lost.
- ETMY yaw damping inclease pitch motion by coupling. It will be improved today.(Ushiba)
- BS oplev is fed back to not only TM but also IM. (Arai)
- WAB: *Akutsu
- Heat consumption is estimated well. 10ppm produce 4W and it will be absorbed by WAB and now it is simulated by heater.
- Equilibrium temperature was 21K.
- Damping became to strong in low temperature.
- Wire of RM was broken on SR3 during tightening clamp.
- CAL: *Yamamoto
- line injection is being tested.
Work plan (*:responsible person)
- IFO: *Izumi, Enomoto, Nakano + many
- Measurement without locking morning, measurement with locking in the afternoon.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
- PR2 had a jump caused by a DAC glitch once a day. Sampling rate will be lowered?
- PR3 also had jumps caused by DAC glitches.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)