Line 11: | Line 11: |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/12(Thur.) === | === 2018/4/20(Fri.) === |
Line 55: | Line 55: |
* IFO: Enomoto, Nagano, Nagano * 5 front gate valve opened and beam was verified at the Y end baffle PD. * Beam shift was only ~10urad when the gate valve opened. * One of the monitor of gate valve did not work. * Final check at X end was done. * Coil driver for Marionette was changed from low to high. * Damping of ETMX will be tested with HPCD. |
* Phase 1 operation was postponed to 4/28 start and 5/6 end. * VAC: *Kimura * Leak was caused wrong positioned O-ring. The shape of O-ring was deformed. * Pump down started 15:50 yesterday. * Now vacuum gage shows ~30Pa. * VAC: *Inoue, Yokozawa * Vacuum monitor is ready! except for Y arm monitor. * ETMX: *Hasegawa * 0.07Hz was damped well! * Yaw and pitch are < 1urad. * ETMY: *Nakano, Shishido * Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow. * Possibility of heat link for 1.6Hz still remains. * Beam at REFL seemed to be OK. * BS: *Eleonora, Izumi * L2P has been well decoupled! * Global injection point for length control is ready. |
Line 64: | Line 81: |
* IFO: damping work or others. * VAC: closing ETMX door. * Pumping starts tomorrow morning. |
* IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. * VAC: *Kimura * Leak test will be performed and the gate valve will open on weekend if no problem. * Camera: *Inoue, Yokozawa * Tcam of Y end will be ready today. * We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday. * DMG needs some maintenance for DAQ. |
Line 71: | Line 99: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 74: | Line 102: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 78: | Line 106: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 84: | Line 112: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC * Some controls for Michelson * 4/13 morning: Pump down starts. |
|
Line 91: | Line 113: |
* Michelson control * Leak check |
* Michelson control. * Leak check, and fix leaks. * Opening the last gate valve weekend. |
Line 95: | Line 118: |
* Operation | * Michelson control. * 4/28 Operation start |
Line 98: | Line 122: |
Line 111: | Line 134: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/20(Fri.)
* Remote participants by eZuce: None
Report of work (*:responsible person)
- Phase 1 operation was postponed to 4/28 start and 5/6 end.
- VAC: *Kimura
- Leak was caused wrong positioned O-ring. The shape of O-ring was deformed.
- Pump down started 15:50 yesterday.
- Now vacuum gage shows ~30Pa.
- VAC: *Inoue, Yokozawa
- Vacuum monitor is ready! except for Y arm monitor.
- ETMX: *Hasegawa
- 0.07Hz was damped well!
Yaw and pitch are < 1urad.
- ETMY: *Nakano, Shishido
- Pitch and yaw reached 1urad! Internal mode of payload of 1.6Hz dropped down somehow.
- Possibility of heat link for 1.6Hz still remains.
- Beam at REFL seemed to be OK.
- BS: *Eleonora, Izumi
- L2P has been well decoupled!
- Global injection point for length control is ready.
Work plan (*:responsible person)
- IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- Leak test will be performed and the gate valve will open on weekend if no problem.
- Camera: *Inoue, Yokozawa
- Tcam of Y end will be ready today.
- We will have mine works for DMG(*Yamamoto) and leak test(*Kimura, Uchiyama, Saito) at ETMX on Saturday and Sunday.
- DMG needs some maintenance for DAQ.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check, and fix leaks.
- Opening the last gate valve weekend.
- week of 4/23
- Michelson control.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools