Line 11: | Line 11: |
2017/4/10 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180410.png||width=1200}} |
2017/4/17 updated {{attachment:KAGRA/Commissioning/Commissioning_schedule_20180417.png||width=1200}} |
Line 50: | Line 50: |
=== 2018/4/13(Fri.) === | === 2018/4/19(Thur.) === |
Line 55: | Line 55: |
* IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa * Last night, beam was lost caused by a shit at oplev. Installing a view port might introduce the shift on oplev yaw. |
* Phase 1 operation was postponed to 4/28 start. |
Line 59: | Line 58: |
* View port for oplev at ETMX was attached yesterday's afternoon. * All the preparation was done and the door of EXC was closed. * Damping of ETMX will be tested with HPCD. |
* Large leak was found at the door on the cross tube, and started venting ~15:00. It takes almost one day to start fix the door, will be afternoon today. Pump down will start tomorrow morning. * Leak test will be performed on Sunday morning. * ETMX: *Hasegawa * Transfer function of TM to BF is being investigated. * ETMY: *Nakano, Shishido * One of the 1.64 and 1.66 Hz peak was suppressed but other one was not. 1-2urad in yaw, 10urad in pitch. * RMS motion at REFL port is still dominated by ETMY. * BS: *Eleonora, Izumi * We are optimizing diagonalization of L2P filter. Needs more time. RMS ~urad |
Line 64: | Line 73: |
* IFO: damping work or others. | * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. |
Line 67: | Line 78: |
* Pumping down will start ~10am today. | * To fix large and small leaks. |
Line 72: | Line 83: |
* IR: PSL, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 75: | Line 86: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 79: | Line 90: |
* IR: Upstream SR2-3 line, Yend 1F * Green: off |
* IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F |
Line 85: | Line 96: |
* week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2. * Closing EXC. * Some controls for Michelson. * 4/13 morning: Pump down starts. |
|
Line 93: | Line 98: |
* Leak check. * Opening the last gate valve. |
* Leak check, and fix leaks. |
Line 97: | Line 101: |
* Operation | * Opening the last gate valve. * 4/28 Operation start |
Line 100: | Line 105: |
Line 113: | Line 117: |
||27||2018/4/17||[[KAGRA/Commissioning/Weekly/20180417/Agenda|Agenda]]||[[attachment:KAGRA/Commissioning/Schedule/Commissioning_schedule_20180417.xlsx|Schedule]]||[[KAGRA/Commissioning/Weekly/20180417/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2017/4/17 updated
Working people assignment
- *: responsible person
Meetings
Morning meeting
- Date and time: Every weekday, 9AM
- Location: Control room, or eZuce
2018/4/19(Thur.)
* Remote participants by eZuce: Miyoki
Report of work (*:responsible person)
- Phase 1 operation was postponed to 4/28 start.
- VAC: *Kimura
- Large leak was found at the door on the cross tube, and started venting ~15:00. It takes almost one day to start fix the door, will be afternoon today. Pump down will start tomorrow morning.
- Leak test will be performed on Sunday morning.
- ETMX: *Hasegawa
- Transfer function of TM to BF is being investigated.
- ETMY: *Nakano, Shishido
- One of the 1.64 and 1.66 Hz peak was suppressed but other one was not. 1-2urad in yaw, 10urad in pitch.
- RMS motion at REFL port is still dominated by ETMY.
- BS: *Eleonora, Izumi
- We are optimizing diagonalization of L2P filter. Needs more time. RMS ~urad
Work plan (*:responsible person)
- IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
- Damping, BS L2P, restoring alignment.
- VAC: *Kimura
- To fix large and small leaks.
Laser hazard
- [AM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [PM]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: Upstream SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 4/16
- Michelson control.
- Leak check, and fix leaks.
- week of 4/23
- Opening the last gate valve.
- 4/28 Operation start
Issues
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
Meeting for pump down test at ETMX 2 (Minute, Check list)
Meeting for pump down test at ETMX 1 (Minute, Check list)
Meeting for pump down test at Center are (Minute, Check list)
Meeting for pump down and cooling at ETMY3 (Minute, Check list)
Meeting for pump down and cooling at ETMY2 (Minute, Check list)
Meeting for pump down and cooling at ETMY1 (Minute, Check list)
Meeting for closing ETY (Minute)
Meeting about PR2 pitch misalignment (Minute)