Line 12: | Line 12: |
2018/9/18 updated |
|
Line 16: | Line 18: |
* 9/10: 停電対策で真空関係の対応 | * 9/10: 停電対策 * 9/10, 11: 復電作業 |
Line 26: | Line 30: |
* 9/18,19~ メインビームのアラインメントをIXAで行う(横澤) | * 9/12,13~ メインビームのアラインメントをIXAで行う * 9/19: Type-Aを下げる。CRY立会い(牛場、都丸) * ~ 9/20: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸) |
Line 28: | Line 34: |
* 9/12 WAB温度計などの残り作業 * 9/19 ITMX heat link防振 -> 牛場、山田 * 9/25 プロテクター取り外し * その後WAB protector外し |
|
Line 41: | Line 52: |
* 9/18: Type-Aを下げる。CRY立会い(牛場、都丸) * ~ 9/21: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸) |
* 9/19 BRT運搬、それまでに通路撤去 |
Line 50: | Line 60: |
* ITMY: * 10/19 鏡を神岡に輸送 |
|
Line 75: | Line 88: |
=== 2018/9/5(Wed.) === * How about the day and night work on Saturday or Sunday. |
=== 2018/9/27(Thur.) === |
Line 79: | Line 91: |
* Control room: * Fan hut: Miyakawa, Takahashi(ICRR), Enomoto, Izumi, Yokozawa, Kimura, Kokeyama * educe: Takahashi |
* Control room: Miyakawa, Lucian, Anna, Oshino, Yamamoto, Kozakawa, Ogaki, Yokozawa * Fan hut: Furuta * eZuce: |
Line 85: | Line 97: |
|||| ||Before 3PM ||After 3PM|| |||| || |||| |
|||| ||Before 3PM||After 3PM || |||| || |||| |
Line 88: | Line 100: |
||Center||upstream IMM ||IR ||IR || | ||Center||upstream IMM ||IR ||IR || |
Line 90: | Line 102: |
||Center||behinde SR2-3 line||N/A ||IR || ||||X end 1F ||IR ||IR || ||||Y end 1F ||N/A ||N/A || |
||Center||behinde SR2-3 line||N/A ||IR & Green|| ||||X end 1F ||N/A ||IR & Green|| ||||Y end 1F ||N/A ||N/A || |
Line 96: | Line 108: |
* Izumi, Enomoto, Eleonora, | * Commissioning: Izumi, Enomoto, Yokogawa, Sugimoto, Midooka * CAL: Kozakai, Ogai, Tomaru |
Line 99: | Line 112: |
* Leak test will be extended to Friday or Saturday. * Due on mirror will last for a while. It is not sure when we can inject Nitrogen. |
* Measurement of ETMX is going on until 3pm. |
Line 104: | Line 115: |
* Green laser is injected into POP table. The power is 10mW and table is covered for the safety. | * EYA is opening now. |
Line 107: | Line 118: |
* Cable clean up on ETMY will be on Thursday. * |
* Need ETMX calm, so AC will be stopped. |
Line 121: | Line 133: |
||43||2018/9/18||[[KAGRA/Commissioning/Weekly/20180918/Agenda|Agenda]]||[[KAGRA/Commissioning/Phase2/Task/CheckList/VacuumITMX#Schedule|Schedule]]||[[KAGRA/Commissioning/Weekly/20180918/Minute|Minute]]|| || |
KAGRA Commissioning Wiki
Task list
Schedule
2018/9/18 updated
- 8/16(Thur) 12:30 meeting at fan hut.
- 8/23(Thur) 13:10 meeting at fan hut.
- 8/30(Thur) 13:10 meeting at fan hut.
- 9/10: 停電対策
- 9/10, 11: 復電作業
- ITMX:
- 8/20の週: アルミホイルを外す。鏡の測定の位置確認、WABの設定。
- 8/21: IPリリース、調整
- 8/27(Mon) : Closing IXC、同日cryostatの掃除をする。
- 8/28-30: NAB commissioning at IXA
- 8/30(Wed) : Closing IXA by Mira-Pro
- 8/30(Thur)夕方- : pump down、30日にポンプ一台で粗挽き、31日金曜日に本引き
- 9/3-5: leak check
9/11: IXC:φ800及びIXAのフランジ開け
- 9/12,13~ メインビームのアラインメントをIXAで行う
- 9/19: Type-Aを下げる。CRY立会い(牛場、都丸)
- ~ 9/20: Type-A作業終了。もとの高さに戻す。CRY立会い(牛場、都丸)
- 9/11-13 WAB finalize
- 9/12 WAB温度計などの残り作業
9/19 ITMX heat link防振 -> 牛場、山田
- 9/25 プロテクター取り外し
- その後WAB protector外し
9/25~26: IXC:φ800及びIXAのフランジ閉止及び真空引き立ち上げ
- 10/1~2: IXC 真空リーク試験
- ETMX:
- 8/31 冷凍機停止、真空引き続けて加温
- 9/3 or 4 少しだけ大気開放
- 9/5~ 中の様子を見て判断してフル大気開放
- 9/7 大気開放ストップ
- 9-8-10 放置
- 9/11-10/3の期間EXCチェンバーが開く
- 9/11大気開放直後:
- PCalミラー設置(井上)
- EXAの横の扉を開けて、PD設置(横澤)
- 9/19 BRT運搬、それまでに通路撤去
- 9/24 - 9/28:
- PCalビームアラインメント(井上)
- ETMXラフアラインメント(EXA内に入る、榎本)
- EXCにBuffle PDインストール(榎本)
- 10/4~5: EXC φ800フランジ閉止及び真空引き立ち上げ
- 10/9~10: EXC 真空リーク試験、又は10/15~16: EXC 真空リーク試験
- ITMY:
- 10/19 鏡を神岡に輸送
Working people assignment
Meetings
Daily meeting
- Date and time: Every weekday, 1PM
- ~10min, as short as possible
- Location: Control room and Fan hut connected by eZuce
2018/9/27(Thur.)
Attendance
- Control room: Miyakawa, Lucian, Anna, Oshino, Yamamoto, Kozakawa, Ogaki, Yokozawa
- Fan hut: Furuta
- eZuce:
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
||
Center |
PSL |
IR & Green |
IR & Green |
Center |
upstream IMM |
IR |
IR |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2-3 line |
N/A |
IR & Green |
X end 1F |
N/A |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers
- Commissioning: Izumi, Enomoto, Yokogawa, Sugimoto, Midooka
- CAL: Kozakai, Ogai, Tomaru
Transition from morning work (*:responsible person)
- Measurement of ETMX is going on until 3pm.
Report of work (*:responsible person)
- EYA is opening now.
Work plan (*:responsible person)
- Need ETMX calm, so AC will be stopped.
KAGRA/Commissioning/DailyWork << < 2024 / 10 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | 2 | 3 | 4 | 5 | 6 | |
7 | 8 | 9 | 10 | 11 | 12 | 13 |
14 | 15 | 16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 | 26 | 27 |
28 | 29 | 30 | 31 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools