18435
Comment:
|
19385
|
Deletions are marked like this. | Additions are marked like this. |
Line 52: | Line 52: |
=== 2019/3/5(Tue.) === | === 2019/3/7(Thur.) === |
Line 57: | Line 57: |
* 2/28-3/5: Fixing PRMs and SRMs * 3/2-5: Re-alignment * 3/6-7: Closing |
* 2/28-3/15: Health check and maintenance for VIS * --(PRM: One flag was dropped. -> leave it)-- * 3/4-8 PRM: Misalignment does not reach where beam hits damper. * --(3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.)-- * ~3/15 BS: Yaw offset adjustment by hand. -> 3/5-6 * --(3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.)-- * 3/18-19: Re-alignment * 3/19: Closing * 3/20: pump down |
Line 63: | Line 70: |
* 2/25-3/4: Yend WAB finalization * 3/5-6: Closing * 3/6~ : Yend pumpdown 3/6~ |
* --(3/5: EYA remaining works by Enomoto, Inoue.)-- * --(2/25-3/4: Yend WAB finalization)-- * 3/5: --(AOS EY)-- and EX(if they have time) work. * --(3/6: Y end closing (no laser hazard at least in the morning))-- * 3/7: Y end pump down |
Line 72: | Line 81: |
* 2/23-3/10: Xend Pcal finalization 1 * Periscope installation * Beam position by IR and Green * 3/5: ETMX aligned * 3/5-3/10: Xend Pcal finalization 2 * 3/11,12 Xend WAB finalization * 3/19,20, Heatlink etc. |
* --(2/23-3/6: Xend Pcal finalization 1)-- * --(Periscope installation)-- * --(3/6: Beam position by IR and Green)-- * --(3/5 AOS: EY and EX(if they have time) work.)-- * --(3/6: Green X alignment (no IR), and no hazard at Y end.)-- * 3/11, 18,19: Xend WAB finalization. * ~3/15: ETMX tuning. * 3/19: Heatlink etc. * 3/19: ETMX finalization by Takahashi * 3/18,19: ETMX alignement * 3/21 closing |
Line 82: | Line 95: |
* 3/11~ : Night work starts * 2/18-3/22 DRMI commissioning * 3/11-4/5 Y arm commissioning * 3/25-4/5 FPMI commissioning |
* 3/18~ : Night work starts, daily meeting will be moved to 1PM * Summary of work will last for a while in the morning meeting. * 2/18-3/22(?postponed): DRMI commissioning * 3/25-4/19: Y arm commissioning * 3/25-4/19: FPMI commissioning |
Line 94: | Line 108: |
* PR3 was tuned once but oplev was gone again. Needs tuning one more day. * Type A: ETMX seems not healthy. To be fixed the next week. * Type B:Offset on IP of BS was seen but not real motion. * IOO: Beam damp for misalignment of PRM seems not working well. Mirror cannot be tilted well. * CAL: Pcal alignment was done. AOS will finish finalization. We need to confirm scheduling at sitework meeting or commissioning meeting. |
* Pump down for central area was postponed for 2 weeks. * Type B: BS still has some trouble, it was decided to open chamber again. * Type Bp: OSEMs were fixed, and it looks OK. Beam position on QPD was off. PRM needs more tuning and measurement. It will be done in the next week. * Y end temperature became low by 3 degree. * IOO: Found touching AOM driver and fork, and it was making a big group loop. Once it was released the noise became much smaller. |
Line 103: | Line 117: |
* Yend pump down start today. |
KAGRA Commissioning Wiki
Task list
Schedule
Working people assignment
Readiness for the X arm commissioning
https://docs.google.com/spreadsheets/d/1S2gyFkyajlbPXMKCrqJV7181YFHUxUgPRB6SXz4z4jI/edit?usp=sharing
Meetings
Daily Meetings (9AM)
Zoom URL: https://zoom.us/j/7631499341
Weekly Meetings (Tuesday 11AM)
Zoom URL: https://zoom.us/j/6676627462
Daily meeting
- Date and time: Every weekday, 9AM
- First ~10min in the morning meeting, as short as possible
- Location: Control room and Fan hut connected by eZuce
2019/3/7(Thur.)
Schedule
- Center
2/26-27: Venting
- 2/28-3/15: Health check and maintenance for VIS
PRM: One flag was dropped. -> leave it
- 3/4-8 PRM: Misalignment does not reach where beam hits damper.
3/6 PR3: range -> incline by 20-30mrad at mirror because of bistable.
~3/15 BS: Yaw offset adjustment by hand. -> 3/5-6
3/5 afternoon or 3/6 morning: Coolers for ITMs will be stopped for 2-3 hours to change water.
- 3/18-19: Re-alignment
- 3/19: Closing
- 3/20: pump down
- Yend
1/25-2/20: Yend Pcal finalization
3/5: EYA remaining works by Enomoto, Inoue.
2/25-3/4: Yend WAB finalization
3/5: AOS EY and EX(if they have time) work.
3/6: Y end closing (no laser hazard at least in the morning)
- 3/7: Y end pump down
- 3/7,8: leak test
- Xend
2/11-2/14: Xend NAB installation
2/21: Removing FC, Payload release
2/27: ETMX release
2/23-3/6: Xend Pcal finalization 1
Periscope installation
3/6: Beam position by IR and Green
3/5 AOS: EY and EX(if they have time) work.
3/6: Green X alignment (no IR), and no hazard at Y end.
- 3/11, 18,19: Xend WAB finalization.
- ~3/15: ETMX tuning.
- 3/19: Heatlink etc.
- 3/19: ETMX finalization by Takahashi
- 3/18,19: ETMX alignement
- 3/21 closing
- 3/22 Pumping down
- Leak test
- 3/18~ : Night work starts, daily meeting will be moved to 1PM
- Summary of work will last for a while in the morning meeting.
- 2/18-3/22(?postponed): DRMI commissioning
- 3/25-4/19: Y arm commissioning
- 3/25-4/19: FPMI commissioning
Note
Weekend
Report of work
- Pump down for central area was postponed for 2 weeks.
- Type B: BS still has some trouble, it was decided to open chamber again.
- Type Bp: OSEMs were fixed, and it looks OK. Beam position on QPD was off. PRM needs more tuning and measurement. It will be done in the next week.
- Y end temperature became low by 3 degree.
- IOO: Found touching AOM driver and fork, and it was making a big group loop. Once it was released the noise became much smaller.
Work plan
- Yend pump down start today.
KAGRA/Commissioning/DailyWork << < 2024 / 9 > >> |
||||||
---|---|---|---|---|---|---|
Mon | Tue | Wed | Thu | Fri | Sat | Sun |
1 | ||||||
2 | 3 | 4 | 5 | 6 | 7 | 8 |
9 | 10 | 11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 | 21 | 22 |
23 | 24 | 25 | 26 | 27 | 28 | 29 |
30 |
Weekly meeting
- Date and time: Every Tuesday, 11AM
- Location: Meeting room at Hokubukaikan, or eZuce, Polycom
No. |
Date |
Agenda |
Schedule |
Minute |
Files |
|
|
|
|
|
|
62 |
2019/3/5 |
See agenda page |
|
||
61 |
2019/2/19 |
See agenda page |
|
||
60 |
2019/2/5 |
See agenda page |
|
||
59 |
2019/1/29 |
|
|
||
58 |
2019/1/22 |
|
|
||
57 |
2019/1/8 |
|
|
||
56 |
2018/12/25 |
|
|
||
55 |
2018/12/17 |
|
|
||
54 |
2018/12/11 |
|
|
||
53 |
2018/12/4 |
|
|
||
52 |
2018/11/27 |
|
|
||
51 |
2018/11/20 |
|
|
||
50 |
2018/11/13 |
|
|
||
49 |
2018/11/6 |
|
|
||
48 |
2018/10/30 |
|
|
||
47 |
2018/10/23 |
|
|
||
46 |
2018/10/16 |
|
|
||
45 |
2018/10/9 |
|
|||
44 |
2018/10/2 |
|
|||
43 |
2018/9/18 |
|
|||
42 |
2018/9/4 |
|
|||
41 |
2018/8/28 |
|
|||
40 |
2018/8/21 |
|
|||
39 |
2018/8/7 |
|
|||
38 |
2018/7/31 |
|
|||
37 |
2018/7/24 |
|
|||
36 |
2018/7/17 |
|
|||
35 |
2018/7/3 |
|
|||
34 |
2018/6/26 |
|
|||
33 |
2018/6/19 |
|
|||
32 |
2018/6/12 |
|
|||
31 |
2018/6/5 |
|
|||
30 |
2018/5/22 |
|
|||
29 |
2018/5/8 |
|
|||
28 |
2018/5/1 |
|
|||
27 |
2018/4/17 |
|
|||
26 |
2018/4/10 |
|
|||
25 |
2018/4/3 |
|
|||
24 |
2018/3/27 |
|
|||
23 |
2018/3/20 |
|
|||
22 |
2018/3/13 |
|
|||
21 |
2018/3/6 |
|
|||
20 |
2018/2/27 |
|
|||
19 |
2018/2/20 |
|
|||
18 |
2018/2/13 |
|
|||
17 |
2018/2/6 |
|
|||
16 |
2018/1/30 |
|
|||
15 |
2018/1/23 |
|
|||
14 |
2018/1/16 |
|
|||
13 |
2018/1/9 |
|
|||
12 |
2017/12/19 |
|
|||
11 |
2017/12/12 |
|
|||
10 |
2017/11/28 |
|
|||
9 |
2017/11/14 |
|
|||
8 |
2017/11/7 |
|
|||
7 |
2017/10/31 |
|
|||
6 |
2017/10/24 |
|
|||
5 |
2017/10/17 |
|
|||
4 |
2017/10/10 |
|
|
||
3 |
2017/10/3 |
|
|||
2 |
2017/9/26 |
|
|||
1 |
2017/9/19 |
|
|
|
Other meetings
2018/9/3: Extended chief meeting for Arm commissioning Agenda, Minute
2018/8/30: 3rd Meeting for pump down at ITMX (Minute, Check list)
2018/8/23: 2nd Meeting for pump down at ITMX (Minute, Check list)
2018/8/16: Meeting for pump down at ITMX (Minute, Check list)
2018/5/28: Meeting for looking back to phase1 for future of KAGRA as an extended chief meeting.
2018/4/11: Meeting for pump down test at ETMX 2 (Minute, Check list)
2018/4/5: Meeting for pump down test at ETMX 1 (Minute, Check list)
2018/3/14: Meeting for pump down test at Center are (Minute, Check list)
2018/1/18: Meeting for pump down and cooling at ETMY3 (Minute, Check list)
2018/1/17: Meeting for pump down and cooling at ETMY2 (Minute, Check list)
2018/1/10: Meeting for pump down and cooling at ETMY1 (Minute, Check list)
2017/12/13: Meeting for pump down at ETMY (Minute, schedule)
2017/11/27~12/1Commissioning Workshop 2017
2017/11/17: Meeting for closing ETY (Minute)
2017/10/12: Meeting about PR2 pitch misalignment (Minute)
Documents
Communication tools