Differences between revisions 28 and 56 (spanning 28 versions)
Revision 28 as of 2019-12-09 21:09:28
Size: 1030
Editor: miyoki
Comment:
Revision 56 as of 2019-12-10 12:56:50
Size: 2128
Editor: miyoki
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
 * Noise investigation about FFUs in the corner stations by an operator.  * '''Noise investigation about FFUs in the corner stations by an operator'''
Line 5: Line 5:
   *Make marks on FFU switches that are not turned off in MCE, IFI, PRM, PR3, PR2, BS, SR2, SR3, SRM, OMC with "Pink Tape".<<BR>> (Operated FFU / Total FFU) table list is below.<<BR>>130 FFUs will be turned off. This corresponds to 26kW heating power.<<BR>>26kW corresponds to about two water cooler cooling power (2 x 14kW).    *Make marks on FFU switches that are not turned off in MCE, IFI, PRM, PR3, PR2, BS, SR2, SR3, SRM, OMC with "Pink Tape".<<BR>> (Operated FFU / Total FFU) table list is below.<<BR>>130 FFUs will be turned off. This corresponds to 26kW heating power.<<BR>>26kW corresponds to about two water cooler cooling power (2 x 14kW). We expect balance.
Line 7: Line 7:
 || Area Name ||MCE || IFI || PRM || PR3 || PR2 || BS || SR2 || SR3 || SRM || OMC ||
 || Operation/Total ||2/16||2/12 ||2/12 ||4/16 ||4/20 ||4/20||4/20 ||4/16 ||4/16 ||4/16 ||
 || Area Name ||MCF || MCE || IFI || PRM || PR3 || PR2 || BS || SR2 || SR3 || SRM || OMC ||
 || Present (151)/Total(180) ||1/16 || 2/16||12/12 || 12/12 || 16/16 ||20/20 ||20/20||20/20 ||16/16 ||16/16 ||16/16 || several FFUs are disorder ||
 || Remained in Test(35)/Total(180) ||1/16 || 2/16||2/12 ||2/12 ||4/16 ||4/20 ||4/20||4/20 ||4/16 ||4/16 ||4/16 ||
<<BR>>
Line 10: Line 12:
  * Method(1)
   * Take a sensitivity by an operator.
   * 4 people stand by (MCE, IFI, PRM), (PR3, PR2, BS), (SR2, SR3), (SRM OMC) FFU switchs.
   * Turn off almost FFUs at the same time by 4 people, except for pink one.
   * Take the sensitivity again before alignment will change.
   * Check the difference btw FFU operation and almost no FFU operation.
 || IEXYV || IEXYA || IEXYC(1F) || IEXYC(2F) ||
 || Present(2)/Total(10) || Present(2)/Total(10) || Present(2)/Total(10) || Present(4)/Total(14) || <--- KOACH are not included ||
<<BR>>
Line 17: Line 16:
 || Corner Station (1F) ||
 || 180+2x24+ 2x10 = 248 ||
Line 18: Line 19:
   1.#2 Method(1)
    * Take a sensitivity by an operator.
    * 4 people stand by (MCE, IFI, PRM), (PR3, PR2, BS), (SR2, SR3), (SRM OMC) FFU switchs.
    * Turn off almost FFUs at the same time by 4 people, except for pink one.
    * Take the sensitivity again before alignment will change.
    * Check the difference btw FFU operation and almost no FFU operation. <<BR>>
Line 19: Line 26:
  1.#3 Method(2)    * Method(2): If the alignment change is too huge for us to take a sensitivity.
    * We turn off IYC-C and BS-C coolers at the same time when we turn off 130 FFUs.
    * Take sensitivity uegently if possible.
    * Check the temp changes in the corner station.
    * If the temp seems to go down rapidly, we enlarge heating power. If the temp gose up rapidly, we turned on IYC-C again and heat up by heaters.
    * we expect do some try and error for several hours if we encounter serious temp change.
    * If alignment comes back, take sensitivity.
    * If it will take too much time to recover FPMI, we give up this trial.
  

Plans for trial just after ER

  • Noise investigation about FFUs in the corner stations by an operator

    1. Preparation
      • Make marks on FFU switches that are not turned off in MCE, IFI, PRM, PR3, PR2, BS, SR2, SR3, SRM, OMC with "Pink Tape".
        (Operated FFU / Total FFU) table list is below.
        130 FFUs will be turned off. This corresponds to 26kW heating power.
        26kW corresponds to about two water cooler cooling power (2 x 14kW). We expect balance.

    Area Name

    MCF

    MCE

    IFI

    PRM

    PR3

    PR2

    BS

    SR2

    SR3

    SRM

    OMC

    Present (151)/Total(180)

    1/16

    2/16

    12/12

    12/12

    16/16

    20/20

    20/20

    20/20

    16/16

    16/16

    16/16

    several FFUs are disorder

    Remained in Test(35)/Total(180)

    1/16

    2/16

    2/12

    2/12

    4/16

    4/20

    4/20

    4/20

    4/16

    4/16

    4/16


  • IEXYV

    IEXYA

    IEXYC(1F)

    IEXYC(2F)

    Present(2)/Total(10)

    Present(2)/Total(10)

    Present(2)/Total(10)

    Present(4)/Total(14)

    <--- KOACH are not included


  • Corner Station (1F)

    180+2x24+ 2x10 = 248

    1. Method(1)
      • Take a sensitivity by an operator.
      • 4 people stand by (MCE, IFI, PRM), (PR3, PR2, BS), (SR2, SR3), (SRM OMC) FFU switchs.
      • Turn off almost FFUs at the same time by 4 people, except for pink one.
      • Take the sensitivity again before alignment will change.
      • Check the difference btw FFU operation and almost no FFU operation.

    2. Method(2): If the alignment change is too huge for us to take a sensitivity.
      • We turn off IYC-C and BS-C coolers at the same time when we turn off 130 FFUs.
      • Take sensitivity uegently if possible.
      • Check the temp changes in the corner station.
      • If the temp seems to go down rapidly, we enlarge heating power. If the temp gose up rapidly, we turned on IYC-C again and heat up by heaters.
      • we expect do some try and error for several hours if we encounter serious temp change.
      • If alignment comes back, take sensitivity.
      • If it will take too much time to recover FPMI, we give up this trial.

KAGRA/EngineeringRun/ER191217_24/postERtrial (last edited 2020-01-05 17:30:32 by tatsuki.washimi)