|| Dec/10-16 (commissioning and preparation) || Dec/17 tune FPMI for longer operation || Dec/17(AM 9) start || | || Dec/10-16 || Commissioning and preparation || || Dec/17 || Concentrate longer stable operation of FPMI || || Dec/17(17:00) || start || || Dec/24(09:00) || end || || Dec/24(09:00 ~ (17:00) ) || proposed post ER tasks || |
ER191217~191224
Time : From 2019/Dec/17(17:00) to 2019/Dec/24(09:00)
- Schedule
Dec/10-16
Commissioning and preparation
Dec/17
Concentrate longer stable operation of FPMI
Dec/17(17:00)
start
Dec/24(09:00)
end
Dec/24(09:00 ~ (17:00) )
proposed post ER tasks
- Subgroup Themes : What will you try and goals for pre-O3 situation.