Line 5: | Line 5: |
* Schedule | * Rough Schedule |
ER191217~191224
Time : From 2019/Dec/17(17:00) to 2019/Dec/24(09:00)
- Rough Schedule
Dec/10-16(09:00)
Commissioning and preparation
Dec/16(09:00)~17/(17:00)
Concentrate longer stable operation of FPMI
Dec/17(17:00)
start
Dec/24(09:00)
end
Dec/24(09:00 ~ (17:00) )
proposed post ER tasks
- Subgroup Themes : What will you try and goals for pre-O3 situation.