Differences between revisions 7 and 16 (spanning 9 versions)
Revision 7 as of 2019-12-09 17:45:30
Size: 788
Editor: miyoki
Comment:
Revision 16 as of 2019-12-10 14:45:52
Size: 1265
Editor: miyoki
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
 * Rough Schedule

 || Dec/10-16(09:00) || Commissioning and preparation ||
 || Dec/16(09:00)~17/(17:00) || Concentrate longer stable operation of FPMI ||
 || Dec/17(17:00) || start ||
 || Dec/24(09:00) || end ||
 || Dec/24(09:00 ~ (17:00) ) || proposed post ER tasks ||
Line 17: Line 25:
  * [[ |Special for LV ? ]]   * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_24/forLV |Special for LV ]]
  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/EngineeringRun/ER191217_24/postERtrial| Post ER trial plans]]

ER191217~191224

KAGRA/EngineeringRun/ER191217_24 (last edited 2019-12-25 13:05:23 by miyoki)