== ER200331~200407 == == ER200401~200407, OBS200407~200421 ==
Line 3: Line 3:
 * Time :''' From 2020/Mar/31(17:00) to 2020/Apr/7(09:00)'''  * Time :''' From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)'''
Line 5: Line 5:
 * Rough Schedule  * Rough Schedule (time can be shifted by 1 or 2 hours according to the task progress and delay)
Line 7: Line 7:
 || Mar/31(~ 09:00) || Commissioning and preparation ||
 || Mar/31(09:00 ~) || IFO stabilization ||
 || Apr/01 || CAL Day 1 (??:00 - ??:00)||
 || Apr/02 || CAL Day 2 (??:00 - ??:00)||
 || Apr/03 || IFO stabilization ||
 || Apr/04 || IFO stabilization ||
 || Apr/05 || IFO stabilization ||
 || Apr/06 || FF(??-??) ||
 || Apr/07(~ 09:00) || ER End ||
 || Apr/07(09:00 ~) || Observation Start ||
 || Mar/29 || Commissioning ||
 || Mar/30 || Commissioning ||
 || Mar/31 || Commissioning, ADS, BPC, IMC angular control, etc ||
 || || ||
 || Mar/31(pm5~) || ER start ||
 || Apr/01 ||(am9-pm5) CAL Day 1, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/02 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 || No JRPC meeting held, only LVEM call||
 || Apr/03 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/04 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/05 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/06 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/07(~am9) || ER end ||
 || || ||
 || Apr/07(am9-pm5) || Maintenance for observation ||
 || Apr/07(pm5~) || Observation Start ||
 || || ||
 || Apr/09 || During Observation || If we got positive results, we hope to ask something about O3c in JRPC meeting ||
 || || ||
 || Apr/16 || During Observation || If we got positive results, we hope to ask something about O3c in JRPC meeting ||
 || || ||
 || Apr/21(~am9) || Observation End ||
 || || ||
 || Apr/21(am9 ~ ) || OMC noise injection and so on ||
Line 20: Line 34:
 * [[KAGRA/EngineeringRun//ER200331-0407/Shift|Shift manuals]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11578|Shift members]]

ER200401~200407, OBS200407~200421

  • Time : From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)

  • Rough Schedule (time can be shifted by 1 or 2 hours according to the task progress and delay)

    Mar/29

    Commissioning

    Mar/30

    Commissioning

    Mar/31

    Commissioning, ADS, BPC, IMC angular control, etc

    Mar/31(pm5~)

    ER start

    Apr/01

    (am9-pm5) CAL Day 1, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/02

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    No JRPC meeting held, only LVEM call

    Apr/03

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/04

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/05

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/06

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/07(~am9)

    ER end

    Apr/07(am9-pm5)

    Maintenance for observation

    Apr/07(pm5~)

    Observation Start

    Apr/09

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/16

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/21(~am9)

    Observation End

    Apr/21(am9 ~ )

    OMC noise injection and so on


For shifts