== ER200331~200407 == == ER200401~200407, OBS200407~200421 ==
Line 3: Line 3:
 * Time :''' From 2020/Mar/31(17:00) to 2020/Apr/7(09:00)'''  * ER Time :''' From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)'''
 * OBS Time :''' From 2020/Apr/7(17:00) to 2020/Apr/21(09:00)'''
Line 5: Line 6:
 * Rough Schedule  * Rough Schedule (time can be shifted by 1 or 2 hours according to the task progress and delay)
Line 7: Line 8:
 || Mar/31(~ 09:00) || Commissioning and preparation ||
 || Mar/31(09:00 ~) || IFO stabilization ||
 || Apr/01 || CAL Day 1 (??:00 - ??:00)||
 || Apr/02 || CAL Day 2 (??:00 - ??:00)||
 || Apr/03 || IFO stabilization ||
 || Apr/04 || IFO stabilization ||
 || Apr/05 || IFO stabilization ||
 || Apr/06 || FF(??-??) ||
 || Apr/07(~ 09:00) || ER End ||
 || Apr/07(09:00 ~) || Observation Start ||
 || Mar/29 || Commissioning ||
 || Mar/30 || Commissioning ||
 || Mar/31 || Commissioning, ADS, BPC, IMC angular control, etc ||
 || || ||
 || Mar/31(pm5~) || ER start ||
 || Apr/01 ||(am9-pm5) CAL Day 1, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/02 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 || No JRPC meeting held, only LVEM call||
 || Apr/03 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/04 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/05 ||(am9-am1) ADS, BPC, IMC angular control, FF adjustment, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/06 ||(am9-am1) Ocean Violence, (am1-am9) silent mode ||
 || Apr/07(~am9) || ER end ||
 || || ||
 || Apr/07(am9-pm5) || Maintenance for observation ||
 || Apr/07(pm5~) || Observation Start ||
 || || ||
 || Apr/09 || During Observation || If we got positive results, we hope to ask something about O3c in JRPC meeting ||
 || || ||
 || Apr/16 || During Observation || If we got positive results, we hope to ask something about O3c in JRPC meeting ||
 || || ||
 || Apr/21(~am9) || Observation End ||
 || || ||
 || Apr/21(am9 ~ ) || Post Observation Activities : OMC noise injection and so on ||
Line 19: Line 34:
=== For shifts ===
 * [[KAGRA/EngineeringRun//ER200331-0407/Shift|Shift manuals]]
=== For shifts for ER and OBS ===
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11578|Shift members]]

----
=== Observation : Points to Remember ===

 * Basic
  * Any problems during Observation will be discussed by Miyoki, Yamamoto, Ito and related group (and SEO members) and we decide the directions. Please report these 3 persons and in "klog" if you notice any problems.
  * If we encounter violent ocean conditions, temporal down of IFO will be selected.
  * Daily morning meeting won't be held during Observation to avoid dense situation. Daily necessary information including from office staffs will be sent via e-mail during 9am-10am.

 * Expected Improvements compared with the previous ER and OBS
  * CAL injection reliability
   * Injection failure is improved ?
  * Initial oplev (mirror alignment) condition at the starting point of relock process
   * Alignment recorder is installed at proper timing during lock acquisition ?
  * ADS/BPC situation
   * Whitch are effective, which should be postponed ?
  * IMC angular control
   * Successful ?
  * ISS stability
   * Improved ? , applying timing is changed ?
  * Expected kick at the unlock timing, and known annoying excitation of a suspension system.
   * Guardian is implemented.
  * Off load status for each suspension.
   * Done according to klog ?
   * How about OMC suspensions ?
  * Summary page reliability is enhanced ?
   * improved ?
  * SAL (monkey) Alignment reliability
   * Dewhitening that might contributes a bit to sensitivity should be included or not ?
   * When should we try SAL (monkey) alignment ?
   * How much IMC output power should be selected ?
  * Additional sound proof for bellows
  * Others

 * Actual tasks during OBS
  * Shift Member Duty and Manual :
   * Basic monitoring and recording (by Miyakawa)
    * Manual (important check points)

  * Maintenance Day Activities (from CAL, DGS, FLC/SAF etc groups)
   * SAF/FCL: Weekly SAF/FCL check will be held in the morning on Tuesday (Furuta, Hayakawa, Yoshimura, Kamioka-mine company)
   * DGS:
   * CAL:
   *

  * '''Restricted Remote Access (from T.Yamamoto)'''
   * We plan to stop the access to controls@k1gate again from 17:00 on 4/7.
   *If you face some emergency, please use your personal accounts in order to login DGS network.
    *> ssh firstname.lastname@172.16.33.11 <mailto:firstname.lastname@172.16.33.11>
   *I ask you to use these personal accounts only for a emergency response.
   *If you need remote access to know the site situation, subsystem status, etc as a daily check, please join to develop remote access tools such as SummaryPage, pastavi etc.
   *Unfortunately, some people probably used these accounts for daily monitoring not for a emergency response during previous run. But we need reliable observing data at least during the observing run.





----
=== Post Observation Tasks : Items and necessary time ===

 * Calibration (~1day) -> Yamamoto
 * Power recycling gain for sidebands (~ 1 day) ->
 * LSC and ASC sensing matrix (~ 2 days) -> Ushiba
 * ISS contribution, frequency noise contribution to DARM (2 days) -> Kokeyama, Miyakawa
 * Finesse/loss measurement for X/Y arm (~ 1 day) ->
 * MICH contrast defect with MICH locked and FPMI locked (~ 1 day) -> Nakano
 * Mode content of AS (OMC cavity scan) (~ 1 day) -> Aso, Kokeyama
 * Scattered light, swing test, IOO investigations (~5days) -> Yokozawa
 * PEM injections (~2day) -> Yokozawa

 * Type Bp measurement with some restricted IFO (~2days) -> Fabian
 * BS measurement with some restricted IFO like simple Michelson (~2days) -> Fabian
 * Type A measurement with some restricted IFO like Xarm (~2days) -> Lucia

 * Feasibility of locking DRFPMI (~ 3 week) -> Nakano

ER200401~200407, OBS200407~200421

  • ER Time : From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)

  • OBS Time : From 2020/Apr/7(17:00) to 2020/Apr/21(09:00)

  • Rough Schedule (time can be shifted by 1 or 2 hours according to the task progress and delay)

    Mar/29

    Commissioning

    Mar/30

    Commissioning

    Mar/31

    Commissioning, ADS, BPC, IMC angular control, etc

    Mar/31(pm5~)

    ER start

    Apr/01

    (am9-pm5) CAL Day 1, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/02

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    No JRPC meeting held, only LVEM call

    Apr/03

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    Apr/04

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    Apr/05

    (am9-am1) ADS, BPC, IMC angular control, FF adjustment, etc, (am1-am9) silent mode for CAL2

    Apr/06

    (am9-am1) Ocean Violence, (am1-am9) silent mode

    Apr/07(~am9)

    ER end

    Apr/07(am9-pm5)

    Maintenance for observation

    Apr/07(pm5~)

    Observation Start

    Apr/09

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/16

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/21(~am9)

    Observation End

    Apr/21(am9 ~ )

    Post Observation Activities : OMC noise injection and so on


For shifts for ER and OBS


Observation : Points to Remember

  • Basic
    • Any problems during Observation will be discussed by Miyoki, Yamamoto, Ito and related group (and SEO members) and we decide the directions. Please report these 3 persons and in "klog" if you notice any problems.
    • If we encounter violent ocean conditions, temporal down of IFO will be selected.
    • Daily morning meeting won't be held during Observation to avoid dense situation. Daily necessary information including from office staffs will be sent via e-mail during 9am-10am.
  • Expected Improvements compared with the previous ER and OBS
    • CAL injection reliability
      • Injection failure is improved ?
    • Initial oplev (mirror alignment) condition at the starting point of relock process
      • Alignment recorder is installed at proper timing during lock acquisition ?
    • ADS/BPC situation
      • Whitch are effective, which should be postponed ?
    • IMC angular control
      • Successful ?
    • ISS stability
      • Improved ? , applying timing is changed ?
    • Expected kick at the unlock timing, and known annoying excitation of a suspension system.
      • Guardian is implemented.
    • Off load status for each suspension.
      • Done according to klog ?
      • How about OMC suspensions ?
    • Summary page reliability is enhanced ?
      • improved ?
    • SAL (monkey) Alignment reliability
      • Dewhitening that might contributes a bit to sensitivity should be included or not ?
      • When should we try SAL (monkey) alignment ?
      • How much IMC output power should be selected ?
    • Additional sound proof for bellows
    • Others
  • Actual tasks during OBS
    • Shift Member Duty and Manual :
      • Basic monitoring and recording (by Miyakawa)
        • Manual (important check points)
    • Maintenance Day Activities (from CAL, DGS, FLC/SAF etc groups)
      • SAF/FCL: Weekly SAF/FCL check will be held in the morning on Tuesday (Furuta, Hayakawa, Yoshimura, Kamioka-mine company)
      • DGS:
      • CAL:
    • Restricted Remote Access (from T.Yamamoto)

      • We plan to stop the access to controls@k1gate again from 17:00 on 4/7.
      • If you face some emergency, please use your personal accounts in order to login DGS network.
      • I ask you to use these personal accounts only for a emergency response.
      • If you need remote access to know the site situation, subsystem status, etc as a daily check, please join to develop remote access tools such as SummaryPage, pastavi etc.

      • Unfortunately, some people probably used these accounts for daily monitoring not for a emergency response during previous run. But we need reliable observing data at least during the observing run.


Post Observation Tasks : Items and necessary time

  • Calibration (~1day) -> Yamamoto

  • Power recycling gain for sidebands (~ 1 day) ->

  • LSC and ASC sensing matrix (~ 2 days) -> Ushiba

  • ISS contribution, frequency noise contribution to DARM (2 days) -> Kokeyama, Miyakawa

  • Finesse/loss measurement for X/Y arm (~ 1 day) ->

  • MICH contrast defect with MICH locked and FPMI locked (~ 1 day) -> Nakano

  • Mode content of AS (OMC cavity scan) (~ 1 day) -> Aso, Kokeyama

  • Scattered light, swing test, IOO investigations (~5days) -> Yokozawa

  • PEM injections (~2day) -> Yokozawa

  • Type Bp measurement with some restricted IFO (~2days) -> Fabian

  • BS measurement with some restricted IFO like simple Michelson (~2days) -> Fabian

  • Type A measurement with some restricted IFO like Xarm (~2days) -> Lucia

  • Feasibility of locking DRFPMI (~ 3 week) -> Nakano