ER200401~200407

  • Time : From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)

  • Rough Schedule

    Mar/29

    Commissioning

    Mar/30

    Commissioning

    Mar/31

    Commissioning, IFO stabilization

    Mar/31(17:00)

    ER start

    Apr/01

    CAL Day 1 (09:00 - 17:00), IFO stabilization

    Apr/02

    CAL Day 2 (09:00 - 17:00), IFO stabilization

    No JRPC meeting held, only LVEM call

    Apr/03

    IFO stabilization

    Apr/04

    IFO stabilization

    Apr/05

    IFO stabilization

    Apr/06

    FF(??-??), IFO stabilization

    Apr/07(09:00)

    ER end

    Apr/07(09:00-17:15)

    Maintenance for observation

    Apr/07(17:00 ~)

    Observation Start

    Apr/09

    During Observation

    If we got positive results, we hope ask something about O3c in JRPC meeting

    Apr/21(~09:00)

    Observation End

    Apr/21(09:00 ~ )

    OMC noise injection and so on


For shifts