== ER200401~200407 == == ER200401~200407, OBS200407~200421 ==
Line 3: Line 3:
 * Time :''' From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)'''  * ER Time :''' From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)'''
 * OBS Time :''' From 2020/Apr/7(17:00) to 2020/Apr/21(09:00)'''
Line 13: Line 14:
 || Apr/02 ||(am9-pm5) CAL Day 2, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode || No JRPC meeting held, only LVEM call||
 || Apr/03 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/04 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/05 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/02 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 || No JRPC meeting held, only LVEM call||
 || Apr/03 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/04 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/05 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 ||
Line 23: Line 24:
 || Apr/09 || During Observation || If we got positive results, we hope ask something about O3c in JRPC meeting ||  || Apr/09 || During Observation || If we got positive results, we hope to ask something about O3c in JRPC meeting ||
 || || ||
 || Apr/16 || During Observation || If we got positive results, we hope to ask something about O3c in JRPC meeting ||
Line 32: Line 35:
 * [[KAGRA/EngineeringRun//ER200331-0407/Shift|Shift manuals]]  * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11578|Shift members]]

ER200401~200407, OBS200407~200421

  • ER Time : From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)

  • OBS Time : From 2020/Apr/7(17:00) to 2020/Apr/21(09:00)

  • Rough Schedule (time can be shifted by 1 or 2 hours according to the task progress and delay)

    Mar/29

    Commissioning

    Mar/30

    Commissioning

    Mar/31

    Commissioning, ADS, BPC, IMC angular control, etc

    Mar/31(pm5~)

    ER start

    Apr/01

    (am9-pm5) CAL Day 1, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/02

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    No JRPC meeting held, only LVEM call

    Apr/03

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    Apr/04

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    Apr/05

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    Apr/06

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/07(~am9)

    ER end

    Apr/07(am9-pm5)

    Maintenance for observation

    Apr/07(pm5~)

    Observation Start

    Apr/09

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/16

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/21(~am9)

    Observation End

    Apr/21(am9 ~ )

    OMC noise injection and so on