== ER200401~200407 == == ER200401~200407, OBS200407~200421 ==
Line 3: Line 3:
 * Time :''' From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)'''  * ER Time :''' From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)'''
 * OBS Time :''' From 2020/Apr/7(17:00) to 2020/Apr/21(09:00)'''
Line 14: Line 15:
 || Apr/03 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/04 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/05 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/06 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode ||
 || Apr/03 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/04 ||(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/05 ||(am9-am1) ADS, BPC, IMC angular control, FF adjustment, etc, (am1-am9) silent mode for CAL2 ||
 || Apr/06 ||(am9-am1) Ocean Violence, (am1-am9) silent mode ||
Line 29: Line 30:
 || Apr/21(am9 ~ ) || OMC noise injection and so on ||  || Apr/21(am9 ~ ) || Post Observation Activities : OMC noise injection and so on ||
Line 33: Line 34:
=== For shifts ===
 * [[KAGRA/EngineeringRun//ER200331-0407/Shift|Shift manuals]]
=== For shifts for ER and OBS ===
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11578|Shift members]]

----
=== Observation : Points to Remember ===

 *
 * Daily morning meeting won't be held during Observation to avoid dense situation. Necessary information including from office staff will be sent via mail during 9am-10am.
 * Shift Member Duty and Manual (from Miyakawa) :
  *

 * Maintenance Day Activities (from CAL, DGS, FLC/SAF group)
  * Saf/FAL: Weekly FCL check will be held in the morning on Tuesday (Furuta, Hayakawa, Yishimura, Kamioka-mine company)
  * DGS:
  * CAL:

 * Restricted Remote Access (from T.Yamamoto) :
  * We plan to stop the access to controls@k1gate again from 17:00 on 4/7.
  *If you face some emergency, please use your personal accounts in order to login DGS network.
   *> ssh firstname.lastname@172.16.33.11 <mailto:firstname.lastname@172.16.33.11>
  *I ask you to use these personal accounts only for a emergency response.
  *If you need remote access to know the site situation, subsystem status, etc as a daily check, please join to develop remote access tools such as SummaryPage, pastavi etc.
  *Unfortunately, some people probably used these accounts for daily monitoring not for a emergency response during previous run. But we need reliable observing data at least during the observing run.


----
=== Post Observation Tasks : Items and necessary time ===

 *
 *
 *
 *
 *

ER200401~200407, OBS200407~200421

  • ER Time : From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)

  • OBS Time : From 2020/Apr/7(17:00) to 2020/Apr/21(09:00)

  • Rough Schedule (time can be shifted by 1 or 2 hours according to the task progress and delay)

    Mar/29

    Commissioning

    Mar/30

    Commissioning

    Mar/31

    Commissioning, ADS, BPC, IMC angular control, etc

    Mar/31(pm5~)

    ER start

    Apr/01

    (am9-pm5) CAL Day 1, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode

    Apr/02

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    No JRPC meeting held, only LVEM call

    Apr/03

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    Apr/04

    (am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2

    Apr/05

    (am9-am1) ADS, BPC, IMC angular control, FF adjustment, etc, (am1-am9) silent mode for CAL2

    Apr/06

    (am9-am1) Ocean Violence, (am1-am9) silent mode

    Apr/07(~am9)

    ER end

    Apr/07(am9-pm5)

    Maintenance for observation

    Apr/07(pm5~)

    Observation Start

    Apr/09

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/16

    During Observation

    If we got positive results, we hope to ask something about O3c in JRPC meeting

    Apr/21(~am9)

    Observation End

    Apr/21(am9 ~ )

    Post Observation Activities : OMC noise injection and so on


For shifts for ER and OBS


Observation : Points to Remember

  • Daily morning meeting won't be held during Observation to avoid dense situation. Necessary information including from office staff will be sent via mail during 9am-10am.
  • Shift Member Duty and Manual (from Miyakawa) :
  • Maintenance Day Activities (from CAL, DGS, FLC/SAF group)
    • Saf/FAL: Weekly FCL check will be held in the morning on Tuesday (Furuta, Hayakawa, Yishimura, Kamioka-mine company)
    • DGS:
    • CAL:
  • Restricted Remote Access (from T.Yamamoto) :
    • We plan to stop the access to controls@k1gate again from 17:00 on 4/7.
    • If you face some emergency, please use your personal accounts in order to login DGS network.
    • I ask you to use these personal accounts only for a emergency response.
    • If you need remote access to know the site situation, subsystem status, etc as a daily check, please join to develop remote access tools such as SummaryPage, pastavi etc.

    • Unfortunately, some people probably used these accounts for daily monitoring not for a emergency response during previous run. But we need reliable observing data at least during the observing run.


Post Observation Tasks : Items and necessary time