Time : From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)
- Rough Schedule (time can be shifted by 1 or 2 hours according to the task progress and delay)
Mar/29
Commissioning
Mar/30
Commissioning
Mar/31
Commissioning, ADS, BPC, IMC angular control, etc
Mar/31(pm5~)
ER start
Apr/01
(am9-pm5) CAL Day 1, (rest time) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode
Apr/02
(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode for CAL2
No JRPC meeting held, only LVEM call
Apr/03
(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode
Apr/04
(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode
Apr/05
(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode
Apr/06
(am9-am1) ADS, BPC, IMC angular control, etc, (am1-am9) silent mode
Apr/07(~am9)
ER end
Apr/07(am9-pm5)
Maintenance for observation
Apr/07(pm5~)
Observation Start
Apr/09
During Observation
If we got positive results, we hope to ask something about O3c in JRPC meeting
Apr/16
During Observation
If we got positive results, we hope to ask something about O3c in JRPC meeting
Apr/21(~am9)
Observation End
Apr/21(am9 ~ )
OMC noise injection and so on