|| Mar/31 || Commissioning and preparation || || Apr/01 || CAL Day 1 (09:00 - ??:00), IFO stabilization|| || Apr/02 || CAL Day 2 (??:00 - ??:00), IFO stabilization|| |
|| Mar/29 || Commissioning || || Mar/30 || Commissioning || || Mar/31 || Commissioning, IFO stabilization|| || Mar/31(17:00) || ER start || || Apr/01 || CAL Day 1 (09:00 - 17:00), IFO stabilization|| || Apr/02 || CAL Day 2 (09:00 - 17:00), IFO stabilization|| No JRPC meeting held, only LVEM call|| |
Line 13: | Line 16: |
|| Apr/06 || FF(??-??) || || Apr/07(~ 09:00) || ER End || || Apr/07(09:00 ~) || Observation Start || |
|| Apr/06 || FF(??-??), IFO stabilization || || Apr/07(09:00) || ER end || || Apr/07(09:00-17:15) || Maintenance for observation || || Apr/07(17:00 ~) || Observation Start || || || || || Apr/09 || During Observation || If we got positive results, we hope ask something about O3c in JRPC meeting || || || || || Apr/21(~09:00) || Observation End || || Apr/21(09:00 ~ ) || OMC noise injection and so on || |
ER200401~200407
Time : From 2020/Apr/1(09:00) to 2020/Apr/7(09:00)
- Rough Schedule
Mar/29
Commissioning
Mar/30
Commissioning
Mar/31
Commissioning, IFO stabilization
Mar/31(17:00)
ER start
Apr/01
CAL Day 1 (09:00 - 17:00), IFO stabilization
Apr/02
CAL Day 2 (09:00 - 17:00), IFO stabilization
No JRPC meeting held, only LVEM call
Apr/03
IFO stabilization
Apr/04
IFO stabilization
Apr/05
IFO stabilization
Apr/06
FF(??-??), IFO stabilization
Apr/07(09:00)
ER end
Apr/07(09:00-17:15)
Maintenance for observation
Apr/07(17:00 ~)
Observation Start
Apr/09
During Observation
If we got positive results, we hope ask something about O3c in JRPC meeting
Apr/21(~09:00)
Observation End
Apr/21(09:00 ~ )
OMC noise injection and so on