Differences between revisions 23 and 24
Revision 23 as of 2022-08-19 14:52:33
Size: 7176
Editor: miyoki
Comment:
Revision 24 as of 2022-08-19 14:57:30
Size: 7163
Editor: miyoki
Comment:
Deletions are marked like this. Additions are marked like this.
Line 125: Line 125:
(1) Suspension health check for PRM/2/3/ BS SRM/2/3 IMMT1/2: (Takahashi-san and Ushiba-kun and selected people) (1) Suspension health check for SRM/2/3 and BS: (Takahashi-san and Ushiba-kun and selected people)

2022/08/05


(1) Suspension health check for PRM/2/3/ BS SRM/2/3 IMMT1/2: (Takahashi-san and Ushiba-kun and selected people)


A01: Cable check:

  • Abnormal cabling は使ってないか、あとで、直せる。

A02: Porality Check

  • All are identified using a magnet meter. So different with each other (PRM/2/3)
  • Why the only one "N" is selected in PR2 for the bottom filter? -> maybe a mistake. -> we cannot recover this situation.今後はconceptを統一してください。ばらばらにならないように。

A03: Rubbing Check

  • According to inspection by camera etc, at present gaps are enough.
  • When the height position is adjusted, the gap can be small.
  • concept of earthquake stop:
    • Smaller is required to avoid a magnet-drop accident.(IM/TM)
    • Some should have larger to avoid accidental touching. (BF)

A04: Range and Calibration (Actuators performance check)

  • PR3 case, the range seems to be small.
    • we should avoid stuck during the range check. So we avoided in PR3. Please add this information in the page.
  • How much are these ranges affected by temperature?
    • Heaters are enough to compensate? It is difficult to test in the air.

A05: Watchdog Settings

A06: Height Setting (Mirror Position) -> Beam paths

  • Finished yesterday.
    • each keystone position was measured.
    • What is the conversion factor?
    • values are the setpoints. These input values should not change as long as we touch the hardware. calibration can vary.

A08: LVDT Calibration and performance

  • value distribution is so large. Why?
    • demodulation phase? gain adjustment? Takahashi-san did not make LVDT. He just checked calibration.
    • LVDT noise/comparison with ADC noise?
  • OSEM

A09: Spectrum

  • IN1: counts values.
  • Healthy spectrum? How to judge?
  • Spectrum with some damping control (aligned state)
  • IM/PR2 shows a different spectrum.
  • Noise floor for high-frequency range is OK.
  • 制御あり無しでとってほしかった。なしのほうもとっているので、あとで、準備。

A10: Transfer Function

  • BFD: Bp系はBFV以外はみな同じ感じ。
  • IML:Bp系はVertical 以外は同じ感じ。Verticalは違う。IMP/Yはかなり個性がある。

  • GASはBFのPRM3が共振が大きい?(page 5)
  • page9: 比較は難しいのではないか?このプロットで言えるのは、共振周波数などが同じなので、こすってないとかしか言えないのでは。

A11: Traverser performance and safety protection

  • According to the work during off-loading in klog, they can be smoothly worked.
  • The limit SW test was avoided by moving actual traverser. Limit SW


(2)Oplev Check for PRM/2/3/ BS SRM/2/3, except for inevitably removed poles/optics for vacuum parts setting. (Yokozawa-kun)


Beam Power

  • 0.7-0.8 mW input:

Beam Path Clearance

  • PRM: has a large gap.
  • PR2: checked.
  • PR3: Next week's homework.

QPD centering

  • Done.

Calibration

  • Done.

PYL Separation(after pumping?)

Spectrum Health

Oplev beam's stray light influence

  • almost no light.

Covering

  • we will do this after closing.

PSD power suppliers will be put in other places. Thermometer set



2022/08/19


(1) Suspension health check for SRM/2/3 and BS: (Takahashi-san and Ushiba-kun and selected people)


A01: Cable check:

A02: Porality Check

A03: Rubbing Check

A04: Range and Calibration (Actuators performance check)

A05: Watchdog Settings

A06: Height Setting (Mirror Position) -> Beam paths

A08: LVDT Calibration and performance

A09: Spectrum

A10: Transfer Function


(2)Oplev Check for PRM/2/3/ BS SRM/2/3, except for inevitably removed poles/optics for vacuum parts setting. (Yokozawa-kun)


Beam Power

Beam Path Clearance

QPD centering

Calibration

PYL Separation(after pumping?)

Spectrum Health

Oplev beam's stray light influence

Covering

PSD power supplier wll be put on other places. Thermometer set


(3)Mid-size Baffles (Akutsu-kun and his selected persons)


Positioning accuracy.


(4)Beam Path (Ushiba-kun, Tanaka-kun?, Hirose-san?)


Main beam - IR beam hit and through around the center (or acceptable area) of optics from inside IFI tank -> SRM.

GR beam - GR beam hit and through around the center (or acceptable area) of optics?

  • (assuming GR beam on POP/POS also pass through around the center (or acceptable area) of optics)

IR from the misaligned PRM - Does it hit on the Dumper? - The misaligned position repeatability is good or well controlled by oplev/something?

Relative positions btw Mid-size baffles and IR/GR.

AR-SRM reflection beam control - Where is the reflected beam from SRM? When misaligned, should it hit the mid-size baffle on SR2 or other? Should we make it possible to align SRM even if it has less reflectivity for RSE?


(5)IFI-IMMT tank


Stray light mitigation(Akutus-kun and selected persons) - The predicted stray beams are dumped? - Is there any missing stray beam paths?

ISS beam/CWP reflection beam extracting (??) - the beam paths are clear? - The beams hit around the center of windows? - The reflected beams on the windows are dumped?

(The IFI new poles seem to be dangerous due to the vibration made by drilling.)

Beam dumper(Akutsu-kun and selected pesrons) - Does the thermometer works?


(6)Vacuum system (Kimura-san / Uchiyama-kun and their selected persons)


Numbering for all ports.

Check the flange seal surface condition.

Decide where the elastomer/Metal gasket will be used.

Top hat seal surface check for SRM/2/3 BS PRM/2/3.

ICF152 flange preparation for the new reducer flanges at SRM/PRM.

Check dust/fungus in stocked tubes/bellows.


(7)Cleanness of Mirrors HR/AR


FC was done for all mirrors' HR/AR, except for OMC Typ-C mirrors.

Check the surfaces and inside again before closing, and blow/absorb as much as possible if you find anything.


(8)Vacuum tank cleaning


In Basic, the cleaning was done after FC. Check inside again and clean just before closing if you find something.


(9) MICH performance


Can we obtain MICH fringe with the aligned ITMX/Y and BS at the REFL PD? Should we lock MICH using REFL PD?


(10)misc


Put Si plate for the dust monitoring? (Si plates/holders were bought well before.)

Mirror View Camera Should we recognize the view image under the bright condition? (Which parts can be seen where in the image.)

Are there any leaning materials on the suspension support frame!?

Are there any stressful cablings on flanges?

KAGRA/IFOIntegration2022/2022MICHClosing (last edited 2022-09-16 16:10:22 by miyoki)