Line 5: Line 5:
  *   * Electrical wirings
   * Coil resistances
   * Isolation of Wiring from coils to flanges(pico and mag-coil)
   * Fixing on tables is tight and reliable?
  * Mechanical Motion
   * Smooth pico motion and its default position
   * Smooth Mag-coil motion and balance and TFs
    * balance can be adjusted after closing?
   * Gaps between magnets and coils
   * Gaps between EQ stoppers and mirrors

 * Mirror conditions
  * Clean around the center?
   * MCe has a spot near the center. But its influence is expected to be small.
Line 8: Line 21:
  * TEM00 flashing
  * The IMC trans beam is the same as before?
  * Beam positions on each mirror
   * They should be the same because the IMC trans was recovered in MCio?
   * How about on MCe?
  * QPD path and centering
  * Gaps between magnets and coils again
  * IP1/2 dynamic range check for the IMC injection?
  * Beam paths for IMC REFL.
Line 9: Line 31:
 *  *Beam damping
  * Beam shield reinstallation
  * Beam dampers were additionally added?

 * Vacuum
  * Cleaning
   * No dust inside, especially on the bottom?
  * Leak point was fastened tightly?
   * It will be done when the bellows are attached by Mirapro.
  * MCE trans flange rotation
  * Lift-up tool check for bellows installation.
  * Flange surface check to avoid leaking especially on GV_mcf


IMC Ecovery(20240322)


  • Suspensions
    • Electrical wirings
      • Coil resistances
      • Isolation of Wiring from coils to flanges(pico and mag-coil)
      • Fixing on tables is tight and reliable?
    • Mechanical Motion
      • Smooth pico motion and its default position
      • Smooth Mag-coil motion and balance and TFs
        • balance can be adjusted after closing?
      • Gaps between magnets and coils
      • Gaps between EQ stoppers and mirrors
  • Mirror conditions
    • Clean around the center?
      • MCe has a spot near the center. But its influence is expected to be small.
  • Alignment
    • TEM00 flashing
    • The IMC trans beam is the same as before?
    • Beam positions on each mirror
      • They should be the same because the IMC trans was recovered in MCio?
      • How about on MCe?
    • QPD path and centering
    • Gaps between magnets and coils again
    • IP1/2 dynamic range check for the IMC injection?
    • Beam paths for IMC REFL.
  • Beam damping
    • Beam shield reinstallation
    • Beam dampers were additionally added?
  • Vacuum
    • Cleaning
      • No dust inside, especially on the bottom?
    • Leak point was fastened tightly?
      • It will be done when the bellows are attached by Mirapro.
    • MCE trans flange rotation
    • Lift-up tool check for bellows installation.
    • Flange surface check to avoid leaking especially on GV_mcf