IMC Ecovery(20240322)
- Suspensions(R.Takahashi)
- Electrical wirings
- Coil resistances and inductances
- Isolation of Wiring from coils to flanges(pico and mag-coil)
- Fixing on tables is tight and reliable?
- Mechanical Motion
- Smooth pico motion and its default position
- Smooth Mag-coil motion and balance and TFs
- balance can be adjusted after closing?
Health MCo: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28890
Health MCi: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28889
Health MCe: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28915
- Gaps between magnets and coils
- Gaps between EQ stoppers and mirrors
- Electrical wirings
- Mirror conditions(Y.Aso)
- Clean around the center?
- MCe has a spot near the center. But its influence is expected to be small.
- Clean around the center?
- Alignment(T.Akutsu, T.Ushiba, T.Yokozawa)
- TEM00 flashing
- The IMC trans beam is the same as before?
- Beam positions on each mirror
- They should be the same because the IMC trans was recovered in MCio?
- How about on MCe? MCE tra QPD can be the reference.
- QPD path and centering
- Gaps between magnets and coils again
- IP1/2 dynamic range check for the IMC injection?
- Beam paths for IMC REFL.
- Beam damping(T.Akutsu)
- Beam shield reinstallation
- Beam dampers were additionally added?
- Vacuum, etc (N.Kimura, T.Uchiyama, S.Miyoki)
- Cleaning
- No dust inside, especially on the bottom?
- Leak point was fastened tightly?
- It will be done when the bellows are attached by Mirapro.
- MCE trans flange rotation
- Lift-up tool check for bellows installation.
- Flange surface check to avoid leaking especially on GV_mcf
- FFU stop for the MCE/MCREFL optical table and reconstruction of the window shield (MCE, MCF?).
- Cleaning