Differences between revisions 56 and 58 (spanning 2 versions)
Revision 56 as of 2024-03-22 14:20:51
Size: 4110
Comment:
Revision 58 as of 2024-03-22 14:23:50
Size: 4185
Comment:
Deletions are marked like this. Additions are marked like this.
Line 57: Line 57:
   * No dust inside, especially on the bottom?
  * Leak point was fastened tightly?
   * No dust inside, especially on the bottom? -> A.I. before closing.
  * Leak point was fastened tightly? -> A.I. before closing.
Line 60: Line 60:
  * MCE trans flange rotation (the past activity is in https://klog.icrr.u-tokyo.ac.jp/osl/?r=28326)   * MCE trans flange rotation (the past activity is in https://klog.icrr.u-tokyo.ac.jp/osl/?r=28326) -> it will be done on Mon.


IMC recovery(20240322)



one of templates for IMC closing by Akutsu-kun in 2021.


??? Recovery(202404??)



??? Recovery(202404??)


KAGRA/IFOIntegration2024/Recovery20240322 (last edited 2024-04-05 16:16:04 by miyoki)