Line 26: Line 26:
   * MCe: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28940 -> Peak of pitch shifted to higher frequency from result of Feb.2. Needs remote centering for the Oplev first (Ushiba).    * MCe: https://klog.icrr.u-tokyo.ac.jp/osl/?r=28940 -> A.I. Peak of pitch shifted to higher frequency from result of Feb.2. Needs remote centering for the Oplev first (Ushiba).
Line 57: Line 57:
   * No dust inside, especially on the bottom?
  * Leak point was fastened tightly?
   * No dust inside, especially on the bottom? -> A.I. before closing.
  * Leak point was fastened tightly? -> A.I. before closing.
Line 60: Line 60:
  * MCE trans flange rotation (the past activity is in https://klog.icrr.u-tokyo.ac.jp/osl/?r=28326)   * MCE trans flange rotation (the past activity is in https://klog.icrr.u-tokyo.ac.jp/osl/?r=28326) -> it will be done on Mon.


IMC recovery(20240322)



one of templates for IMC closing by Akutsu-kun in 2021.


??? Recovery(202404??)



??? Recovery(202404??)