Differences between revisions 243 and 266 (spanning 23 versions)
Revision 243 as of 2018-07-24 18:58:05
Size: 5064
Comment:
Revision 266 as of 2019-04-21 13:52:02
Size: 4976
Editor: 157
Comment:
Deletions are marked like this. Additions are marked like this.
Line 4: Line 4:
=== Date: July 25(Wed) ~ July 27(Fri), 2018 === === Date: May 8(Wed) ~ 10(Fri), 2019 ===
Line 29: Line 29:
{{{#!wiki comment/dotted
Line 30: Line 32:
 * We will use ICRR car for the transportation between Excel Hotel Toyama and KAGRA site.  * We will use the ICRR car for the transportation between Excel Hotel Toyama and KAGRA site.
Line 33: Line 35:
}}}
Line 34: Line 37:
||||||||▄▄▄▄▄▄▄▄▄▄▄▄▄ July 25 ▄▄▄▄▄▄▄▄▄▄▄▄▄ ||
||||||||▄▄▄▄▄▄▄▄▄▄▄▄▄ May 8 ▄▄▄▄▄▄▄▄▄▄▄▄▄ ||
Line 36: Line 40:
||||KAGRA visit by ICRR car (accompany person: Kokeyama)|| ||||KAGRA visit by ICRR car ||
Line 38: Line 42:

{{{#!wiki comment/dotted
Line 49: Line 56:
||||Moving to Tokyo by airplane (accompany person: Miyakawa)|| ||||Moving to Tokyo by airplane (accompany person: ooooo)||
Line 52: Line 59:

}}}
Line 57: Line 66:
||||||||▄▄▄▄▄▄▄▄▄▄▄▄▄ July 26 ▄▄▄▄▄▄▄▄▄▄▄▄▄ || ||||||||▄▄▄▄▄▄▄▄▄▄▄▄▄ May 9 ▄▄▄▄▄▄▄▄▄▄▄▄▄ ||
Line 63: Line 72:
||9:30-9:50||Purpose of this PAB and Status of KAGRA||Ohashi||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8495|o]]||
||9:50-10:10||Project management and SEO activities||Saito||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8491|o]]||
||9:30-9:50||Purpose of this PAB and Status of KAGRA||Kajita||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||9:50-10:10||Project management and SEO activities||Saito||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||10:10-11:40||Responses to the recommendation by PAB201
8||Ohashi||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
Line 66: Line 76:
||10:40-11:10||Report of bKAGRA-1 run and commissioning tasks||Miyakawa||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8492|o]]||
||11:10-11:40||b
KAGRA plan (Roadmap)||Ando||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8503|o]]||
||11:40-12:10||bKAGRA schedule||Uchiyama||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8497|o]]||
||12:10-12:40||KAGRA safety||Miyoki||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8496|o]]||
||11:10-11:40||KAGRA commissioning report||Miyakawa||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||11:
40-12:10||KAGRA Roadmap||Ando||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||12:10-12:40||KAGRA schedule||Uchiyama||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||12:10-12:40||KAGRA upgrade||Aso||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
Line 73: Line 83:
||14:00-16:00||||Report of subgroup 1|| ||
||14:00-14:20||VIS|| Aso ||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8493|o]]||
||14:20-14:40||LAS|| Mio ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8498|o]]||
||14:40-15:00||MIR|| Hirose ||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8499|o]]||
||15:00-15:20||IOO|| Kokeyama ||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8501|o]]||
||14:00-14:30||KAGRA upgrade||Aso||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||14:30-15:00||KSC report||Shinkai||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||15:00-15:30||KAGRA Data Analysis||Tagoshi||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||15:30-16:00||KAGRA Infrastructure||Miyoki||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||16:00-16:30||KAGRA Safety||TBD||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
Line 79: Line 89:
||15:50-16:10||||Report of subgroup 2|| ||
||16:10-16:3
0||CRY|| Tomaru ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8505|o]]||
||16:30-16:50||MIF|| Izumi ||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8490|o]]||
||16:50-17:10||CAL|| Haino ||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=8494|o]]||
||17:10-17:30||DAS|| Tagoshi ||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=
|x]]||
|||||||| ||
||17:00-17:40||||Report of subgroup || ||
||17:00-17:
20||CRY||Tomaru||[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
||17:20-17:40||DET||Yamamoto ||[[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=|x]]||
Line 87: Line 94:
||18:30-20:30||||||Banquet <<BR>> [[http://www.the-meat-dutch.com/|THE MEAT DUTCH(ミートダッチ)]]|| ||18:30-20:30||||||Banquet <<BR>> [[(TBD)]]||
Line 90: Line 97:
||||||||▄▄▄▄▄▄▄▄▄▄▄▄▄ July 27 ▄▄▄▄▄▄▄▄▄▄▄▄▄ || ||||||||▄▄▄▄▄▄▄▄▄▄▄▄▄ May 10 ▄▄▄▄▄▄▄▄▄▄▄▄▄ ||

Program Advisory Board


Date: May 8(Wed) ~ 10(Fri), 2019

Location: The University of Tokyo Future Center Initiative, 2nd floor, Room 205


Reviewers

Name

Affiliation

Albert Lazzarini (Chair)

LIGO/Caltech

Norna Robertson

LIGO/University of Glasgow

Jo van den Brand

VIRGO/Nikhef

Bangalore Sathyaprakash

Pennsylvania State University

Misao Sasaki

IPMU, University of Tokyo

Junichi Watanabe

NAOJ

Akira Yamamoto

KEK

Jesper Munch

Adelaide University

Chang Hee Nam

IBS Center for Relativistic Laser Science


KAGRA visit

▄▄▄▄▄▄▄▄▄▄▄▄▄ May 8 ▄▄▄▄▄▄▄▄▄▄▄▄▄

KAGRA visit by ICRR car


Program

▄▄▄▄▄▄▄▄▄▄▄▄▄ May 9 ▄▄▄▄▄▄▄▄▄▄▄▄▄

Time

Subject and Title

Speaker

File

9:00-9:30

(Closed session by PAB members only)

9:30-9:50

Purpose of this PAB and Status of KAGRA

Kajita

x

9:50-10:10

Project management and SEO activities

Saito

x

10:10-11:40

Responses to the recommendation by PAB2018

Ohashi

x

30min Break

11:10-11:40

KAGRA commissioning report

Miyakawa

x

11:40-12:10

KAGRA Roadmap

Ando

x

12:10-12:40

KAGRA schedule

Uchiyama

x

12:10-12:40

KAGRA upgrade

Aso

x

12:40-14:00

Lunch

14:00-14:30

KAGRA upgrade

Aso

x

14:30-15:00

KSC report

Shinkai

x

15:00-15:30

KAGRA Data Analysis

Tagoshi

x

15:30-16:00

KAGRA Infrastructure

Miyoki

x

16:00-16:30

KAGRA Safety

TBD

x

30min Break

17:00-17:40

Report of subgroup

17:00-17:20

CRY

Tomaru

x

17:20-17:40

DET

Yamamoto

x

17:30-18:30

(Closed session by PAB members only)
Question from PAB

18:30-20:30

Banquet
(TBD)

▄▄▄▄▄▄▄▄▄▄▄▄▄ May 10 ▄▄▄▄▄▄▄▄▄▄▄▄▄

Time

Subject and Title

Speaker

File

9:00-11:00

Response to PAB Quetions

11:00-12:00

(Closed session by PAB members only)

12:00-13:00

Comment from PAB

13:30

Adjourn