Line 3: Line 3:
* PCAL works are planned on a specific weekday per month and per XY. The dates are,
 * July ? and ?
 * Aug 28 and 29
 * Sep ? and ?
 * Oct ? and ?
 * Nov ? and ?
 * PCAL works are planned on a specific weekday per month and per XY. The dates are,
  * July 23 and 24
  * Aug 28 and 29
  * Sep 24 and 25
  * Oct 21 and 22
  * Nov 26 and 27
Line 10: Line 10:
* The expected schedule is as follows,
 * 09:00 Attend the KAGRA morning meeting in front of the KAGRA tunnel
 * 09:30 Enter the mine after obtaining approval during the meeting
 * (12:00 Usually, I continue working without a lunch break to save time.)
 * 15:00 Finish calibration work at the End station
 * 16:00 Complete parameter updates at the Center area or control room
 * The expected one day schedule is as follows,
  * 09:00 Attend the KAGRA morning meeting in front of the KAGRA tunnel
  * 09:30 Enter the mine after obtaining approval during the meeting
  * 12:00 Usually, I continue working without a lunch break to save time.)
  * 15:00 Finish calibration work at the End station
  * 16:00 Complete parameter updates at the Center area or control room

Dan-kun and Hido-kun will perform PCAL activities on specific days on weekdays at X or Y end. So, one of the shift members is expected to accompany him in AM and PM.

  • PCAL works are planned on a specific weekday per month and per XY. The dates are,
    • July 23 and 24
    • Aug 28 and 29
    • Sep 24 and 25
    • Oct 21 and 22
    • Nov 26 and 27
  • The expected one day schedule is as follows,
    • 09:00 Attend the KAGRA morning meeting in front of the KAGRA tunnel
    • 09:30 Enter the mine after obtaining approval during the meeting
    • 12:00 Usually, I continue working without a lunch break to save time.)
    • 15:00 Finish calibration work at the End station
    • 16:00 Complete parameter updates at the Center area or control room