Line 25: Line 25:
 * X-Pcal homeworks
  *
Line 33: Line 31:

 * TMSX optical system (Akutsu and his selected persons)


IYC Recovery(20240407)


  • Suspension health check (Takahashi, Ushiba)
    • A01: Cable check
    • A02 Porality Check
    • A03 Rubbing Check
    • A04: Range and Calibration
    • A05: Watchdog Setting: Skip
    • A06: Height Measurement
    • A08: Calibration:skip

    • A09: Spectrum(spectra of IM/MN photosensors.)
    • A10: Transfer Function
  • Oplev Check (Yokozawa, Akutsu)
  • Green flash at REFL and Trans PD
  • Windows Cleaning
  • Tcam (Yokozawa and ChenDan, and Yamamoto)

  • Baffle PDs (Yokozawa and his selected persons):
  • NAB, WAB (Akutsu)
  • Vacuum system (Kimura-san / Uchiyama-kun and their selected persons)
    • tie rod adjustment between EXC and TMSX to avoid stress when the only EXC side is pumped down.
    • Nasty air parts were replaced.
    • Vacuum alert recovery after pumping down.
    • GV interlock will be tried after pumping down.
    • The broken cc-10 was replaced.
    • N2 purge is necessary for EXV.
  • Cryo-system (Kimura-san and his selected persons)
    • All temp signals are obtained?
    • Connector change is required for the heat link suspensions.
    • Cryocon alert to slack after cooling.
    • No interlock for TMP around the Cryostat.