Differences between revisions 2 and 7 (spanning 5 versions)
Revision 2 as of 2024-04-09 09:47:22
Size: 1292
Editor: miyoki
Comment:
Revision 7 as of 2024-04-12 10:28:28
Size: 1544
Comment:
Deletions are marked like this. Additions are marked like this.
Line 6: Line 6:
   *    * Re-cabling of BF damper
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28993
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29177
Line 8: Line 10:
   *    * Magnet gluing
   * https://klog.icrr.u-tokyo.ac.jp/osl/?r=28831
Line 10: Line 13:
   *    * judge by the transfer functions
Line 15: Line 18:
   *    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29064
Line 18: Line 21:
   *    * ITMY IM/MN photosensors: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29140
   * ITMY tower sensor: https://klog.icrr.u-tokyo.ac.jp/osl/?r=29141
Line 20: Line 24:
   *    * https://klog.icrr.u-tokyo.ac.jp/osl/?r=29138
Line 22: Line 26:
  *
Line 39: Line 44:
  * tie rod adjustment between EXC and TMSX to avoid stress when the only EXC side is pumped down.
Line 43: Line 47:
  * The broken cc-10 was replaced.
* N2 purge is necessary for EXV.
  * N2 purge is necessary for IYV.
Line 48: Line 51:
  * Connector change is required for the heat link suspensions.


IYC Recovery(20240407)


KAGRA/Recovery2024/IYC (last edited 2024-04-15 12:31:12 by TakashiUchiyama)