Line 30: Line 30:
 * [[KAGRA/Subgroups/AEL/Rackcheck/BS|BS]] Not checked yet!  * [[KAGRA/Subgroups/AEL/Rackcheck/BS|BS]]
  *
Not checked yet!
Line 33: Line 34:
  * Not installed
Line 35: Line 37:
  * Not installed
Line 37: Line 40:
  * Not installed
Line 39: Line 43:
  * Not installed
Line 41: Line 46:
  * Not checked yet!(No connection??)
Line 43: Line 49:
  * Not checked yet!(No connection??)
Line 45: Line 52:
  * Not installed
Line 47: Line 55:
  * Not installed
Line 49: Line 58:
  * Not installed

 * [[KAGRA/Subgroups/AEL/Rackcheck/ASC0|ASC0]]
  * Not installed
Line 51: Line 64:
  * Not installed
Line 53: Line 67:
  * Not checked yet!
Line 55: Line 70:
  * Not checked yet!
Line 57: Line 73:
  * Not checked yet!
Line 59: Line 76:
  * Not checked yet!
Line 89: Line 107:
  * Not checked yet!

List of KAGRARacks

  • IOO

    • Not checked yet!
  • IMC

    • Not checked yet!
  • PR2

    • Checked(2018/05/25)
    • Summarize the report (2018/06/06 : Tomura)
    • Summarize the problem point (ONGOING : Yokozawa)
    • Reprot to expert (Discuss, who?)
    • Rack fix progress (Not finished)
  • PR3 Checked, not fixed yet (2018/06/06)

    • Checked(2018/05/25)
    • Summarize the report (2018/06/06 : Tomura)
    • Summarize the problem point (ONGOING : Yokozawa)
    • Reprot to expert (Discuss, who?)
    • Rack fix progress (Not finished)
  • PRM Checked, not fixed yet (2018/06/06)

    • Checked(2018/05/25)
    • Summarize the report (2018/06/06 : Tomura)
    • Summarize the problem point (ONGOING : Yokozawa)
    • Reprot to expert (Discuss, who?)
    • Rack fix progress (Not finished)
  • BS

    • Not checked yet!
  • IX0

    • Not installed
  • IX1

    • Not installed
  • IY0

    • Not installed
  • IY1

    • Not installed
  • SR2

    • Not checked yet!(No connection??)
  • SR3

    • Not checked yet!(No connection??)
  • SRM

    • Not installed
  • OMC

    • Not installed
  • LSC

    • Not installed
  • ASC0

    • Not installed
  • ASC1

    • Not installed
  • EX0

    • Not checked yet!
  • EX1_1

    • Not checked yet!
  • EX1_2

    • Not checked yet!
  • EX1_PWR

    • Not checked yet!
  • EY0

    • Checked(2018/06/01)
    • Summarize the report (2018/06/06 : Tomura)
    • Summarize the problem point (ONGOING : Yokozawa)
    • Reprot to expert (Discuss, who?)
    • Rack fix progress (Not finished)
  • EY1_1

    • Checked(2018/06/01)
    • Summarize the report (2018/06/06 : Tomura)
    • Summarize the problem point (ONGOING : Yokozawa)
    • Reprot to expert (Discuss, who?)
    • Rack fix progress (Not finished)
  • EY1_2

    • Checked(2018/06/01)
    • Summarize the report (2018/06/06 : Tomura)
    • Summarize the problem point (ONGOING : Yokozawa)
    • Reprot to expert (Discuss, who?)
    • Rack fix progress (Not finished)
  • EY1_PWR

    • Checked(2018/06/01)
    • Summarize the report (2018/06/06 : Tomura)
    • Summarize the problem point (ONGOING : Yokozawa)
    • Reprot to expert (Discuss, who?)
    • Rack fix progress (Not finished)
  • XARM500

    • Not checked yet!