= 20181117 = = 20181107 =
Line 5: Line 5:
 * Workers around the NAB: Akutsu, Yano, Simon, K. Tanaka
 * Helpers: Hayakawa, Nakata
Line 6: Line 8:
 * Took out the NAB suspension.
  * Opened the aluminum pack which covered the NAB suspension in the wooden box (only one-side opened) on the "jambo" cargo.
  * Detached some screws which fixed one of the wooden foot beams to the wooden box; the wooden foot beams were for fixing the assembly frame of the NAB suspension structure.
  * Using the portable gantry crane ([[http://www.asada.co.jp/product/s785307.html|Sumner S785103]]), which was brought from NAOJ, hanged up the NAB suspension slightly. Two slings and four eyebolts were used (one sling for two eyebolts).
  * Moved the cargo to open space under the hanged NAB suspension.
  * Lifted down

20181107

  • [[]]

Today's activities

  • Workers around the NAB: Akutsu, Yano, Simon, K. Tanaka
  • Helpers: Hayakawa, Nakata
  • Took out the NAB suspension.
    • Opened the aluminum pack which covered the NAB suspension in the wooden box (only one-side opened) on the "jambo" cargo.
    • Detached some screws which fixed one of the wooden foot beams to the wooden box; the wooden foot beams were for fixing the assembly frame of the NAB suspension structure.
    • Using the portable gantry crane (Sumner S785103), which was brought from NAOJ, hanged up the NAB suspension slightly. Two slings and four eyebolts were used (one sling for two eyebolts).

    • Moved the cargo to open space under the hanged NAB suspension.
    • Lifted down

Next Plan