* Took out the NAB suspension. * Opened the aluminum pack which covered the NAB suspension in the wooden box (only one-side opened) on the "jambo" cargo. * Detached some screws which fixed one of the wooden foot beams to the wooden box; the wooden foot beams were for fixing the assembly frame of the NAB suspension structure. * Using the portable gantry crane ([[http://www.asada.co.jp/product/s785307.html|Sumner S785103]]), which was brought from NAOJ, hanged up the NAB suspension slightly. Two slings and four eyebolts were used (one sling for two eyebolts). * Moved the cargo to open space under the hanged NAB suspension. * Lifted down |
20181107
- [[]]
Today's activities
- Workers around the NAB: Akutsu, Yano, Simon, K. Tanaka
- Helpers: Hayakawa, Nakata
- Took out the NAB suspension.
- Opened the aluminum pack which covered the NAB suspension in the wooden box (only one-side opened) on the "jambo" cargo.
- Detached some screws which fixed one of the wooden foot beams to the wooden box; the wooden foot beams were for fixing the assembly frame of the NAB suspension structure.
Using the portable gantry crane (Sumner S785103), which was brought from NAOJ, hanged up the NAB suspension slightly. Two slings and four eyebolts were used (one sling for two eyebolts).
- Moved the cargo to open space under the hanged NAB suspension.
- Lifted down
Next Plan