= 20180921 = * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6269]] * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6250]] == Today's activities == Workers: Akutsu, K. Nagano, T. Tanaka, N. Fujii * Shown in the above links and the below. * [[KAGRA/Subgroups/AOS/TMSX_O3/2018-09-21/PreparationForTMSXOpticInstallation|Preparation For TMSX Optic Installation part2]] == Next plan == * Repairing some damaged parts * Replace the damages actuator coils. * Lay cables for TMS and TMS-VIS * Need to count the required number and length of the cables (on Sept 26??). * Configure the digital models properly. * Engage the logical channels and the assigned physical channels. * Install geophones. * Install TMS-VIS into the chamber. * Install BRT on it. * Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.) See [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9015|here]]. == Wanted! == * Tester!! lend from DGS or PEM?? * First contact to clean the side diameter of the optics.