= 20180926 = * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6310]] * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=6312]] == Today's activities == Workers: Akutsu, Uraguchi, K. Nagano, Hasegawa, T. Tanaka * Finally have installed the TMS-VIS. == Next plan == * Detach white tapes and release the cables. * Connect the cables to flanges. * Configure the digital models properly. * Engage the logical channels and the assigned physical channels. * Check the signal integrity * To do so, the hanged table should move slightly. * But never jump to it, as we need to install the BRT on TMS-VIS; we need rather a rigid stage when we torque screws to fix BRT to TMS-VIS. * So, Uraguchi-san suggested the procedure. It should be docuented later. It is a little bit complicated about the dummy weights and restraints and new shims. * Install BRT on TMS-VIS. * Clean the sides of the optics to be installed into the vacuum chamber. (Ethanol+Acetone wiping with vectra alpha, then First Contact.) See [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9015|here]]. == Wanted! == * Tester!! lend from DGS or PEM?? * M8 eyebolts for managing the dummy weight plates... * First contact to clean the side diameter of the optics. * Need a signal generator for LVDTs