20190604
Today's activities
- Workers (AM): Akutsu, Uraguchi, K. Tanaka, Furuta, Kamioka-Kougyou, Hayakawa, Nakada, Tamori
- Workers (PM): Akutsu, Uraguchi, K. Tanaka, Nakada, Tamori
This morning we accepted the TMS-VIS-Y and the accompanying parts (see here).
This afternoon we took out the BRT-Y from the EXT chamber along with the fixed table (see here)..
Next Plan
- Check the brought load.
- Attach the geophones
- Check the electric connections.
Wanted!
- 1t chain block for the portal crane to pick up the load from the palette.
- Slings and Shuckles for picking up the load from the palette.
- (Blue) levelers.
- Laser level at Xend.