 * This afternoon we took out the BRT-Y from the EXT chamber with the fixed table.  * This afternoon we took out the BRT-Y from the EXT chamber along with the fixed table (see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=9083|here]])..

20190604

Today's activities

  • Workers (AM): Akutsu, Uraguchi, K. Tanaka, Furuta, Kamioka-Kougyou, Hayakawa, Nakada, Tamori
  • Workers (PM): Akutsu, Uraguchi, K. Tanaka, Nakada, Tamori
  • This morning we accepted the TMS-VIS-Y and the accompanying parts (see here).

  • This afternoon we took out the BRT-Y from the EXT chamber along with the fixed table (see here)..

Next Plan

  • Check the brought load.
  • Attach the geophones
  • Check the electric connections.

Wanted!

  • 1t chain block for the portal crane to pick up the load from the palette.
  • Slings and Shuckles for picking up the load from the palette.
  • (Blue) levelers.
  • Laser level at Xend.