Line 3: | Line 3: |
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=9100]] | |
Line 8: | Line 9: |
* This morning we * This afternoon we |
* This morning we unpacked the aluminum foil covering the TMS-VIS * This afternoon we checked the TMS-VIS whether it would be injured or not, and seemed safe. After attaching six geophones, so we installed it into the EYT chmaber. |
Line 12: | Line 13: |
* Check the brought load. * Attach the geophones * Check the electric connections. |
* Install the BRT. * Balancing * Alignment |
20190605
Today's activities
- Workers (AM): Akutsu, Uraguchi, K. Tanaka, Takahashi (ICRR)
- Workers (PM): Akutsu, Uraguchi, K. Tanaka, Simon
- This morning we unpacked the aluminum foil covering the TMS-VIS
- This afternoon we checked the TMS-VIS whether it would be injured or not, and seemed safe. After attaching six geophones, so we installed it into the EYT chmaber.
Next Plan
- Install the BRT.
- Balancing
- Alignment
Wanted!
- Laser level at Xend or the corner station.