 * Summary of CAL analysis meeting(Yuki)
 * Status of KAGRA observation and commissioning break (Takahiro)
 * updates of Low latency (S.Takahiro)
  * Improve the measured points (Inoue)
  * Do we need the quick analysis for commissioning break?-> dont need it. (Yamamoto-san)
 * Summary of CAL analysis meeting(Yuki)[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11536|slide]]
  * HF OMC effect
  * Pcal requiere 61usec x3?-> 61usec x2
  * Consistency check with L_A.
 * Status of KAGRA observation and commissioning break (Y.Takahiro)
 * Consistency check of h(t) (Y.Takahiro)
  * Offline analysis(C00<->C01<->C10<->C20; S.Takahiro or Darkhan?)
  * Comparing with Rx module (Analysis of last week measurement: Inoue)
 * Updates of Low latency (S.Takahiro)
Line 8: Line 16:
  * Goal
   * Installation of the Gcal systems
    * NCU Gcal was developed. We shiped the system to AS today.
    * Feng-kai, Chang-I joined KAGRA officially. They will come Japan for instllation work (1st visit: May, Second visit: July). Depend on the corona virses problem.
   * Fixing the Y-end Pcal optics -> Depend on the timing of chamber opening
   * Noise probrem of X-end PCAL -> independent task from IFO
    * Escitation port? We should charactarize it after we install new OFS and 20bit DAQ system.
   * Improvement of OFS -> independent task from IFO
    * Installed to NCU and Toyama uni. for Charactarization: Ko-Han and Ito
   * Instllation of Backup Server
 * Shift
Line 11: Line 30:
  * 3/17 WSK measurement?

2020/3/9

17:00 JST (Japan) 16:00 CST (Taiwan) 9:00 CET (Geneva)

  • Discussion of maintenance day plan 16:00-17:00 [Yamamoto・Darkhan]
    • Improve the measured points (Inoue)
    • Do we need the quick analysis for commissioning break?-> dont need it. (Yamamoto-san)

  • Summary of CAL analysis meeting(Yuki)slide

    • HF OMC effect
    • Pcal requiere 61usec x3?-> 61usec x2

    • Consistency check with L_A.
  • Status of KAGRA observation and commissioning break (Y.Takahiro)
  • Consistency check of h(t) (Y.Takahiro)
    • Offline analysis(C00<->C01<->C10<->C20; S.Takahiro or Darkhan?)

    • Comparing with Rx module (Analysis of last week measurement: Inoue)
  • Updates of Low latency (S.Takahiro)
  • Preparing of O4(Yuki)
    • Goal
      • Installation of the Gcal systems
        • NCU Gcal was developed. We shiped the system to AS today.
        • Feng-kai, Chang-I joined KAGRA officially. They will come Japan for instllation work (1st visit: May, Second visit: July). Depend on the corona virses problem.
      • Fixing the Y-end Pcal optics -> Depend on the timing of chamber opening

      • Noise probrem of X-end PCAL -> independent task from IFO

        • Escitation port? We should charactarize it after we install new OFS and 20bit DAQ system.
      • Improvement of OFS -> independent task from IFO

        • Installed to NCU and Toyama uni. for Charactarization: Ko-Han and Ito
      • Instllation of Backup Server
  • Shift
    • 2/25(Tue.) [Ogaki・Inoue]
    • 3/3 (Tue.) [Ogaki・Darkhan]
    • 3/10 (Tue.) [Yamamoto・Darkhan・Yuki (remote)]
    • 3/17 WSK measurement?
    • 3/24 CAL day(Tue.) [Yamamoto・Darkhan]
    • 3/31(Tue.) [Yamomoto・Darkhan]