2020/3/9
17:00 JST (Japan) 16:00 CST (Taiwan) 9:00 CET (Geneva)
- Discussion of maintenance day plan 16:00-17:00 [Yamamoto・Darkhan]
- Improve the measured points (Inoue)
Do we need the quick analysis for commissioning break?-> dont need it. (Yamamoto-san)
Summary of CAL analysis meeting(Yuki)slide
- HF OMC effect
Pcal requiere 61usec x3?-> 61usec x2
- Consistency check with L_A.
- Status of KAGRA observation and commissioning break (Y.Takahiro)
- Consistency check of h(t) (Y.Takahiro)
Offline analysis(C00<->C01<->C10<->C20; S.Takahiro or Darkhan?)
- Comparing with Rx module (Analysis of last week measurement: Inoue)
- Updates of Low latency (S.Takahiro)
- Preparing of O4(Yuki)
- Goal
- Installation of the Gcal systems
- NCU Gcal was developed. We shiped the system to AS today.
- Feng-kai, Chang-I joined KAGRA officially. They will come Japan for instllation work (1st visit: May, Second visit: July). Depend on the corona virses problem.
Fixing the Y-end Pcal optics -> Depend on the timing of chamber opening
Noise probrem of X-end PCAL -> independent task from IFO
- Escitation port? We should charactarize it after we install new OFS and 20bit DAQ system.
Improvement of OFS -> independent task from IFO
- Installed to NCU and Toyama uni. for Charactarization: Ko-Han and Ito
- Instllation of Backup Server
- Measurement of upper suspension driver, Low temperature effect
- Offline analysis for O3b catalog paper.
- Installation of the Gcal systems
- Goal
- Shift
- 2/25(Tue.) [Ogaki・Inoue]
- 3/3 (Tue.) [Ogaki・Darkhan]
- 3/10 (Tue.) [Yamamoto・Darkhan・Sawada]
- 3/17 WSK measurement [Yamamoto,Darkhan]
- 3/24 CAL day(Tue.) [Yamamoto・Darkhan・Yuki (remote)]
- 3/16 Discussion of CAL day contents 17:00-
- 3/31(Tue.) [Yamomoto・Darkhan・Yuki (remote)]