Line 3: | Line 3: |
* Duotone 36Hz and 960Hz are inconsistnt. * Pcal-XY time delay and Swept sine injection are consistent within 1 sigma error. * herr/C00 and hctrl/C00 is also consistent. * Mod_Fil include S-Z. * Mod_Fil include resG29(). * 5 days parameter estimation wiht swept sine. |
CAL meeting 20200608
Yuki & S.Takahiro Final decision of C20 h(t)
- Duotone 36Hz and 960Hz are inconsistnt.
- Pcal-XY time delay and Swept sine injection are consistent within 1 sigma error.
- herr/C00 and hctrl/C00 is also consistent.
- Mod_Fil include S-Z.
- Mod_Fil include resG29().
- 5 days parameter estimation wiht swept sine.
- Yuki: Action item list for C21 (Deadline: End of August(Before LVK meeting))
- Followings are list of update.
- Time correction (Sawada?)
- Data analysis of injection test (Sawada?)
- 17sec problem (Site: Yamamoto, Chen-Dan?)
- Time trend of WSK (Ko-Han and Ito?)
- Estimation of H_PCAL (Yuki?)
- Beam position (Chen-Dan?)
Improvement of the measured filter parameters (Steven & Hsiang-Yu?)
- Followings are list of update.
- Sawada: Current status of C20 h(t) production
- Yuki: Shipping of GCAL(Mid. July?)