Line 3: Line 3:
 * Commissioning schedule based on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]]  . Commissioning schedule from [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]]
Line 7: Line 7:
 * Before ETMY CRYp installation
  * CAL Task: Lab test on the CRYp actuators
  * People: Miyamoto, Ushiba, Inoue, Tomaru +CRY
==== Before ETMY CRYp installation ====
 . CAL Task: '''Lab test on the CRYp actuators'''
 . People: '''Miyamoto, Ushiba, Inoue, Tomaru''' +CRY
Line 11: Line 11:
 * 2017.10.31 ETMY CRYp installed
  * Return the beam from ETMY to BS
  * CAL Task: What we can do for the calibration with a single arm ?
==== 2017.10.31 ETMY CRYp installed ====
 . Return the beam from ETMY to BS
 . CAL Task: '''What we can do for the calibration with a single arm ?'''
Line 15: Line 15:
 * 2017.11.22- ETMY evacuation
 * 2017.12.8 cool down starts
  * CAL Task: ETMY monitoring with HR-camera
  * People: Inoue, Haino +CRY
==== 2017.11.22- ETMY evacuation ====
==== 2017.12.8 cool down starts ====
 . CAL Task: '''ETMY monitoring with HR-camera'''
 . People: '''Inoue, Haino''' +CRY
Line 20: Line 20:
 * 2018.2.2 ETMX CRYp installed
  *
Return the beam from ETMX to BS
  * Lock room temperature Michelson
  * CAL Tasks:
   * Measurement of optical efficiency
  
* Measurement of open-loop transfer function
  
* Implementation of online h(t) generator
   *
People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS
==== 2018.2.2 ETMX CRYp installed ====
 .
Return the beam from ETMX to BS
 . Lock room temperature Michelson
 . CAL Tasks:
 * '''Measurement of optical efficiency'''
* '''Measurement of open-loop transfer function'''
* '''Implementation of online h(t) generator'''
 .
People: '''Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura''' +MIF,DGS
Line 29: Line 29:
 * 2018.2.13- ETMX evacuation
 * 2018.3.2 cool down starts
   * CAL Task: Monitor of actuator efficiency during cool down
   * People: Miyamoto, Ushiba, Inoue, Haino, Tomaru +CRY
==== 2018.2.13- ETMX evacuation ====
==== 2018.3.2 cool down starts ====
 . CAL Task: '''Monitor of actuator efficiency during cool down'''
 . People: '''Miyamoto, Ushiba, Inoue, Haino, Tomaru''' +CRY
Line 34: Line 34:
 * By 2018.3.31 Start observation run with 3-km cryogenic Michelson
   * CAL Tasks:
    * Measurement and evaluation of time variation of optical and actuator efficiencies
    * In which frequency we should excite the calibration lines ?
   * People: Yamamoto, Miyamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS subgroups
==== By 2018.3.31 Start observation run with 3-km cryogenic Michelson ====
 . CAL Tasks:
 * '''Measurement and evaluation of time variation of optical and actuator efficiencies'''
 * '''In which frequency we should excite the calibration lines ?'''
 . People: '''Yamamoto, Miyamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura''' +MIF,DGS subgroups
Line 41: Line 41:
 * Shorten PR2-PR3 length by 2.4 cm (at max)
 * Re-alignment
 * connect remaining bellows/ducts and evacuate central area
 * Lock cryogenic PRMI
  * Cal Tasks: Redo the calibration
   * Measurement of optical efficiency
   * Measurement of open-loop transfer function
  * People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS
 . Shorten PR2-PR3 length by 2.4 cm (at max)
 . Re-alignment
 . connect remaining bellows/ducts and evacuate central area
 . Lock cryogenic PRMI
 . Cal Tasks: '''Redo the calibration'''
 * '''Measurement of optical efficiency'''
 * '''Measurement of open-loop transfer function'''
 . People: '''Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura''' +MIF,DGS

bKAGRA Calibration Tasks and people

Phase1 (before the deadline: Mar/2017)

Before ETMY CRYp installation

  • CAL Task: Lab test on the CRYp actuators

  • People: Miyamoto, Ushiba, Inoue, Tomaru +CRY

2017.10.31 ETMY CRYp installed

  • Return the beam from ETMY to BS
  • CAL Task: What we can do for the calibration with a single arm ?

2017.11.22- ETMY evacuation

2017.12.8 cool down starts

  • CAL Task: ETMY monitoring with HR-camera

  • People: Inoue, Haino +CRY

2018.2.2 ETMX CRYp installed

  • Return the beam from ETMX to BS
  • Lock room temperature Michelson
  • CAL Tasks:
  • Measurement of optical efficiency

  • Measurement of open-loop transfer function

  • Implementation of online h(t) generator

  • People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS

2018.2.13- ETMX evacuation

2018.3.2 cool down starts

  • CAL Task: Monitor of actuator efficiency during cool down

  • People: Miyamoto, Ushiba, Inoue, Haino, Tomaru +CRY

By 2018.3.31 Start observation run with 3-km cryogenic Michelson

  • CAL Tasks:
  • Measurement and evaluation of time variation of optical and actuator efficiencies

  • In which frequency we should excite the calibration lines ?

  • People: Yamamoto, Miyamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS subgroups

Phase1 (after the deadline: Mar/2017)

  • Shorten PR2-PR3 length by 2.4 cm (at max)
  • Re-alignment
  • connect remaining bellows/ducts and evacuate central area
  • Lock cryogenic PRMI
  • Cal Tasks: Redo the calibration

  • Measurement of optical efficiency

  • Measurement of open-loop transfer function

  • People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS