⇤ ← Revision 1 as of 2016-11-18 03:59:39
1897
Comment:
|
2019
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
* Commissioning schedule based on [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]] | . Commissioning schedule from [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]] |
Line 7: | Line 7: |
* Before ETMY CRYp installation * CAL Task: Lab test on the CRYp actuators * People: Miyamoto, Ushiba, Inoue, Tomaru +CRY |
==== Before ETMY CRYp installation ==== . CAL Task: '''Lab test on the CRYp actuators''' . People: '''Miyamoto, Ushiba, Inoue, Tomaru''' +CRY |
Line 11: | Line 11: |
* 2017.10.31 ETMY CRYp installed * Return the beam from ETMY to BS * CAL Task: What we can do for the calibration with a single arm ? |
==== 2017.10.31 ETMY CRYp installed ==== . Return the beam from ETMY to BS . CAL Task: '''What we can do for the calibration with a single arm ?''' |
Line 15: | Line 15: |
* 2017.11.22- ETMY evacuation * 2017.12.8 cool down starts * CAL Task: ETMY monitoring with HR-camera * People: Inoue, Haino +CRY |
==== 2017.11.22- ETMY evacuation ==== ==== 2017.12.8 cool down starts ==== . CAL Task: '''ETMY monitoring with HR-camera''' . People: '''Inoue, Haino''' +CRY |
Line 20: | Line 20: |
* 2018.2.2 ETMX CRYp installed * Return the beam from ETMX to BS * Lock room temperature Michelson * CAL Tasks: * Measurement of optical efficiency * Measurement of open-loop transfer function * Implementation of online h(t) generator * People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS |
==== 2018.2.2 ETMX CRYp installed ==== . Return the beam from ETMX to BS . Lock room temperature Michelson . CAL Tasks: * '''Measurement of optical efficiency''' * '''Measurement of open-loop transfer function''' * '''Implementation of online h(t) generator''' . People: '''Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura''' +MIF,DGS |
Line 29: | Line 29: |
* 2018.2.13- ETMX evacuation * 2018.3.2 cool down starts * CAL Task: Monitor of actuator efficiency during cool down * People: Miyamoto, Ushiba, Inoue, Haino, Tomaru +CRY |
==== 2018.2.13- ETMX evacuation ==== ==== 2018.3.2 cool down starts ==== . CAL Task: '''Monitor of actuator efficiency during cool down''' . People: '''Miyamoto, Ushiba, Inoue, Haino, Tomaru''' +CRY |
Line 34: | Line 34: |
* By 2018.3.31 Start observation run with 3-km cryogenic Michelson * CAL Tasks: * Measurement and evaluation of time variation of optical and actuator efficiencies * In which frequency we should excite the calibration lines ? * People: Yamamoto, Miyamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS subgroups |
==== By 2018.3.31 Start observation run with 3-km cryogenic Michelson ==== . CAL Tasks: * '''Measurement and evaluation of time variation of optical and actuator efficiencies''' * '''In which frequency we should excite the calibration lines ?''' . People: '''Yamamoto, Miyamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura''' +MIF,DGS subgroups |
Line 41: | Line 41: |
* Shorten PR2-PR3 length by 2.4 cm (at max) * Re-alignment * connect remaining bellows/ducts and evacuate central area * Lock cryogenic PRMI * Cal Tasks: Redo the calibration * Measurement of optical efficiency * Measurement of open-loop transfer function * People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS |
. Shorten PR2-PR3 length by 2.4 cm (at max) . Re-alignment . connect remaining bellows/ducts and evacuate central area . Lock cryogenic PRMI . Cal Tasks: '''Redo the calibration''' * '''Measurement of optical efficiency''' * '''Measurement of open-loop transfer function''' . People: '''Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura''' +MIF,DGS |
bKAGRA Calibration Tasks and people
Commissioning schedule from JGW-T1605595
Phase1 (before the deadline: Mar/2017)
Before ETMY CRYp installation
CAL Task: Lab test on the CRYp actuators
People: Miyamoto, Ushiba, Inoue, Tomaru +CRY
2017.10.31 ETMY CRYp installed
- Return the beam from ETMY to BS
CAL Task: What we can do for the calibration with a single arm ?
2017.11.22- ETMY evacuation
2017.12.8 cool down starts
CAL Task: ETMY monitoring with HR-camera
People: Inoue, Haino +CRY
2018.2.2 ETMX CRYp installed
- Return the beam from ETMX to BS
- Lock room temperature Michelson
- CAL Tasks:
Measurement of optical efficiency
Measurement of open-loop transfer function
Implementation of online h(t) generator
People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS
2018.2.13- ETMX evacuation
2018.3.2 cool down starts
CAL Task: Monitor of actuator efficiency during cool down
People: Miyamoto, Ushiba, Inoue, Haino, Tomaru +CRY
By 2018.3.31 Start observation run with 3-km cryogenic Michelson
- CAL Tasks:
Measurement and evaluation of time variation of optical and actuator efficiencies
In which frequency we should excite the calibration lines ?
People: Yamamoto, Miyamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS subgroups
Phase1 (after the deadline: Mar/2017)
- Shorten PR2-PR3 length by 2.4 cm (at max)
- Re-alignment
- connect remaining bellows/ducts and evacuate central area
- Lock cryogenic PRMI
Cal Tasks: Redo the calibration
Measurement of optical efficiency
Measurement of open-loop transfer function
People: Yamamoto, Ushiba, Inoue, Haino, Kokeyama, Michimura +MIF,DGS