= Calibration Tasks and Milestones = = Calibration Tasks and Milestones (Towards O3) =
Line 3: Line 3:
== Task (Responsible and sub-responsible person) == === Goals ===
 * Make the whole chain of h(t) reconstruction running with Pcal
  * 3 types of h(t) provide (online, low latency, offline)
  * online h(t) generation using Pcal(DGS)
  * low latency and offline will be similar code
 * Accuracy at the initial LIGO O1 level (10%,10deg.)
  * LIGO also have many try and error
  * free sweging is used for calibration method comparison
  * final goal is 1%, 1deg.
 * By the starting of phase-2 engineering run (well in advance of joining O3)

=== Task (Responsible and sub-responsible person(s)) ===
Line 5: Line 16:
  == Pcal (Y.Inoue) ==
=== Listing-up (S.Haino and responsible people) ===
 * --(List-up tasks and responsible person)--
 * List-up milestones and deadline
 * Submit the list of task and milestone to the KAGRA scheduler

=== Pcal (Y.Inoue, C.Kozakai, Cory, Bin-Hua) ===
Line 9: Line 25:
 * List-up the systematic error budget table for O3
 * Achieve 1% displacement error
 * Absolute power calibration
  * Contact person of working standard of Toyama univ.
  * Absolute calibration organization
 * Maintenance at Kamioka site.
 * BH should stay Kamioka and periodic work
 * Telephoto camera
  * Installation is almost done
  * Maintenance of TCam is done by T.Yokozawa
  * IR filter issue(spare camera), additional spare camera.
  * Image analysis by Tomigami.

=== Front-end (T.Yamamoto, +1person from off-site) ===
 * Make the models for the online h(t) reconstruction [status: ''ongoing'' | expected finish: '''Jan. 1, 2019''']
 * Provide the necessary DAQ channels for the low-latency calibration[status: ''ongoing'' | expected finish: '''Jan. 1, 2019''']
   * The necessary channels had already existed in Phase-1 operation (What we should are only small fix.).
Line 11: Line 44:
== Front-end (T.Yamamoto) ==
 * Make models for the online h(t) reconstruction
 * Provide the necessary DAQ channels for the low-latency calibration
 * ...
=== Low-latency and offline (D.Tuyenbayev, S.Tsuchida, S.Haino) ===
 * Ask to LIGO CAL team for the detailed information of gstlal-calibration (DT) [status: ''ongoing'' | expected finish: '''none''']
 * Make gstlal-calibration running on a machine at KAGRA (DT, SH) [status: ''ongoing'' | expected finish: '''Jul 15''']
   * Find names and versions of all prerequisite libraries
   * Install prerequisites and gstlal-cal package on a machine at AS
   * Test gstlal-cal pipeline on an AS machine
   * Install prerequisites and gstlal-cal package on a machine at KAGRA
   * Test the pipeline on a KAGRA machine
 * Use gstlal-calibration for the offline h(t) reconstruction of bKAGRA phase-1 data (ST, DT) [status: ''to do'' | expected finish: '''Aug 15''']
   * Note: depends on the installation of gstlal-cal on a machine at AS
   * Produce dummy output equivalent to online cal output
   * Compare gstlal and online outputs of bKAGRA phase-1 data
 * Generate status vector (DT, ST, SH) [status: ''to do'' | expected finish: '''Sep 15''']
   * Decide status vector bits
   * Modify (adapt) the function that generates the status vector
   * Produce the status vector data
 * Generation of FIR filters for KAGRA DARM model (ST, DT) [status: ''to do'' | expected finish: '''end of bKAGRA phase-2''']
   * Note: Depends on the readiness of the DARM model
 * Feed KAGRA online channels into gstlal-calibration and generate low-latency h(t) (ST, DT, SH) [status: ''to do'' | expected finish: '''end of bKAGRA phase-2''']
   * Note: Depends on the readiness of DMT
   * Run run the pipeline in low-latency during bKAGRA phase-2
Line 16: Line 66:
== Low-latency and offline (D.Tuyenbayev, S.Haino) ==
 * Ask to LIGO CAL team for the detailed information of gstlal-calibratin
 * Make gstlal-calibration running on any PCs at KAGRA
 * Use gstlal-calibration for the offline h(t) reconstruction of phase-1 data
 * Incorporate KAGRA online h(t) data into gstlal-calibration and generate low-latency h(t)

== DARM model (???, D.Tuyenbayev) ==
 * Make a subway map of the KAGRA DARM model
 * Optimize the calibration lines
 * Coordinate the Open Loop Gain (OLG) Transfer function measurements
 * Estimate and trace the slow time variation of the calibration parameters

== Pcal verification (???) ==
=== DARM model (T.Yamamoto, D.Tuyenbayev, T.Yokozawa) ===
 * Make a subway map of the KAGRA DARM model [status: ''to do'' | expected finish: '''Sep. 1, 2018''']
 * Optimize the calibration lines [status: ''to do'' | expected finish: '''May 1, 2019''']
   * DARM sensitivity is required in order to optimize.
 * Coordinate the Open Loop Gain (OLG) Transfer function measurements [status: ''to do'' | expected finish: '''Apr. 1, 2019''']
   * DARM lock is required because this task contains try and error of the swept sine injection.
 * Estimate and trace the slow time variation of the calibration parameters [status: ''to do'' | expected finish: '''Jun. 1, 2019''']
 * Electronics transfer function. [status: ''to do'' | expected finish: '''Oct. 1, 2018''']
   * The subway map help us to decide the necessary component.
=== Pcal verification (Y.Inoue,...) ===
Line 31: Line 78:
 * Compare h(t)s calculated between diff,common,...
Line 32: Line 80:
== Systematic errors assignment (???, S.Haino) == === Hardware injection (T.Yokozawa, Cory ) ===
 * Make the online model for the hardware injection with actuators[status: ''fist version finished'' | expected finish: '''end of August''']
 * Make the online model for the hardware injection with Pcal[status: ''fist version finished'' | expected finish: '''end of August''']
 * Coordinate the hardware injection tests[status: ''to do'' | expected finish: '''end of bKAGRA phase-2''']
 * Analyze the hardware injected data and verify the DARM subway map[status: ''to do'' | expected finish: '''end of bKAGRA phase-2''']

=== Systematic errors assignment (T.Sawada, Y.Inoue, S.Haino, T.Yokozawa) ===
Line 34: Line 88:
 * Make a simulation.
Line 36: Line 91:
 * (If possible) Incorporate DARM model and parameter uncertainties in the data analysis  * (If possible) Incorporate DARM model and parameter uncertainties in the data analysis    * A.Miyamoto will show the first results of the effect of calibration uncertainties to the POP III data analysis

Calibration Tasks and Milestones (Towards O3)

Goals

  • Make the whole chain of h(t) reconstruction running with Pcal
    • 3 types of h(t) provide (online, low latency, offline)
    • online h(t) generation using Pcal(DGS)
    • low latency and offline will be similar code
  • Accuracy at the initial LIGO O1 level (10%,10deg.)
    • LIGO also have many try and error
    • free sweging is used for calibration method comparison
    • final goal is 1%, 1deg.
  • By the starting of phase-2 engineering run (well in advance of joining O3)

Task (Responsible and sub-responsible person(s))

  • Cross out if the tasks are completed

Listing-up (S.Haino and responsible people)

  • List-up tasks and responsible person

  • List-up milestones and deadline
  • Submit the list of task and milestone to the KAGRA scheduler

Pcal (Y.Inoue, C.Kozakai, Cory, Bin-Hua)

  • Install Pcal at X and Y-end and coordinate the long-term Pcal characterization
  • Prepare for the necessary EPICS channels to the online system for the calibration

  • List-up the systematic error budget table for O3
  • Achieve 1% displacement error
  • Absolute power calibration
    • Contact person of working standard of Toyama univ.
    • Absolute calibration organization
  • Maintenance at Kamioka site.
  • BH should stay Kamioka and periodic work
  • Telephoto camera
    • Installation is almost done
    • Maintenance of TCam is done by T.Yokozawa
    • IR filter issue(spare camera), additional spare camera.
    • Image analysis by Tomigami.

Front-end (T.Yamamoto, +1person from off-site)

  • Make the models for the online h(t) reconstruction [status: ongoing | expected finish: Jan. 1, 2019]

  • Provide the necessary DAQ channels for the low-latency calibration[status: ongoing | expected finish: Jan. 1, 2019]

    • The necessary channels had already existed in Phase-1 operation (What we should are only small fix.).
  • ...

Low-latency and offline (D.Tuyenbayev, S.Tsuchida, S.Haino)

  • Ask to LIGO CAL team for the detailed information of gstlal-calibration (DT) [status: ongoing | expected finish: none]

  • Make gstlal-calibration running on a machine at KAGRA (DT, SH) [status: ongoing | expected finish: Jul 15]

    • Find names and versions of all prerequisite libraries
    • Install prerequisites and gstlal-cal package on a machine at AS
    • Test gstlal-cal pipeline on an AS machine
    • Install prerequisites and gstlal-cal package on a machine at KAGRA
    • Test the pipeline on a KAGRA machine
  • Use gstlal-calibration for the offline h(t) reconstruction of bKAGRA phase-1 data (ST, DT) [status: to do | expected finish: Aug 15]

    • Note: depends on the installation of gstlal-cal on a machine at AS
    • Produce dummy output equivalent to online cal output
    • Compare gstlal and online outputs of bKAGRA phase-1 data
  • Generate status vector (DT, ST, SH) [status: to do | expected finish: Sep 15]

    • Decide status vector bits
    • Modify (adapt) the function that generates the status vector
    • Produce the status vector data
  • Generation of FIR filters for KAGRA DARM model (ST, DT) [status: to do | expected finish: end of bKAGRA phase-2]

    • Note: Depends on the readiness of the DARM model
  • Feed KAGRA online channels into gstlal-calibration and generate low-latency h(t) (ST, DT, SH) [status: to do | expected finish: end of bKAGRA phase-2]

    • Note: Depends on the readiness of DMT
    • Run run the pipeline in low-latency during bKAGRA phase-2

DARM model (T.Yamamoto, D.Tuyenbayev, T.Yokozawa)

  • Make a subway map of the KAGRA DARM model [status: to do | expected finish: Sep. 1, 2018]

  • Optimize the calibration lines [status: to do | expected finish: May 1, 2019]

    • DARM sensitivity is required in order to optimize.
  • Coordinate the Open Loop Gain (OLG) Transfer function measurements [status: to do | expected finish: Apr. 1, 2019]

    • DARM lock is required because this task contains try and error of the swept sine injection.
  • Estimate and trace the slow time variation of the calibration parameters [status: to do | expected finish: Jun. 1, 2019]

  • Electronics transfer function. [status: to do | expected finish: Oct. 1, 2018]

    • The subway map help us to decide the necessary component.

Pcal verification (Y.Inoue,...)

  • Coordinate h(t) calibration with the Free-swinging Michelson method
  • Compare h(t)s calibrated between Free-swinging Michelson and Pcal
  • Compare h(t)s calculated between diff,common,...

Hardware injection (T.Yokozawa, Cory )

  • Make the online model for the hardware injection with actuators[status: fist version finished | expected finish: end of August]

  • Make the online model for the hardware injection with Pcal[status: fist version finished | expected finish: end of August]

  • Coordinate the hardware injection tests[status: to do | expected finish: end of bKAGRA phase-2]

  • Analyze the hardware injected data and verify the DARM subway map[status: to do | expected finish: end of bKAGRA phase-2]

Systematic errors assignment (T.Sawada, Y.Inoue, S.Haino, T.Yokozawa)

  • Estimate the systematic errors due to calibration
  • Make a simulation.
  • Provide the number (amplitude and phase) for the data analysis group
  • Provide the calibration envelopes for the data analysis group
  • (If possible) Incorporate DARM model and parameter uncertainties in the data analysis
    • A.Miyamoto will show the first results of the effect of calibration uncertainties to the POP III data analysis