|| 001 || 2013 Nov. 19 || Sekiguchi, Hirose ||<#ff0000> Urgent!|| Overall design || Ask somebody in LIGO details of the circuit for OSEM. ||2013 Nov. 26|| | || 001 || 2013 Nov. 19 || Sekiguchi, Hirose ||Closed. Takanori and Osamu Miyakawa found the document about OSEM (it includes the schematic design of circuit) by themselves.|| Overall design || Ask somebody in LIGO details of the circuit for OSEM. ||2013 Nov. 26|| |
Cryopayload's Action Item List
General Descriptions
This is a list of action items identified in the cryopayload meeting after its kick-off (2013 Nov 15). If you want to know the previous information or historical path to the cryopayload meetings, please refer to CRY-AOS meeting.
Action Items
A/I# |
Identified on |
Assigned to |
Status/Output |
Related to |
Description |
Due date |
001 |
2013 Nov. 19 |
Sekiguchi, Hirose |
Closed. Takanori and Osamu Miyakawa found the document about OSEM (it includes the schematic design of circuit) by themselves. |
Overall design |
Ask somebody in LIGO details of the circuit for OSEM. |
2013 Nov. 26 |
002 |
2013 Nov. 19 |
R. Takahashi |
Urgent! |
Overall design |
3-D design drawing of Type-A is necessary (ASAP!). Ask to Gianni. |
2013 Nov. 26 |
003 |
2013 Nov. 19 |
R. Takahashi |
Urgent! |
Vertical spring |
About blade metal spring (vertical spring), the schedule and strategy and so on will be summarized by R. Takahashi, Ishizaki, Sekiguchi, and K. Yamamoto, and reported in the next meeting. |
2013 Nov. 26 |
004 |
2013 Nov. 19 |
K. Yamamoto |
Urgent! |
Material |
About the masses, including a recoil mass, intermediate mass, intermediate recoil mass, and platform, the evaluation of the eddy current damping is necessary. K. Yamamoto will ask (1) to Eric Hennes how much he can make his effort for this problem and whether he can provide files for Finite Element Analysis. (2) to Ando or Aso whether Nishi's file for eddy current damping still remains. |
2013 Nov. 26 |
005 |
2013 Nov. 19 |
D. Chen |
Urgent! |
Control |
D. Chen will ask Uchiyama whether a picomotor can survive at cryogenic temperature. |
2013 Nov. 26 |
006 |
2013 Nov. 19 |
D. Chen |
Urgent! |
Control |
D. Chen looks for design drawing of a stage for Type-B, and some commercial stages. |
2013 Nov. 26 |
007 |
2013 Nov. 19 |
K. Yamamoto |
Urgent! |
Control |
The schedule for the control system should be considered again. |
2013 Nov. 26 |
008 |
2013 Nov. 19 |
K. Yamamoto |
Urgent! |
Control |
About the procurement of the OSEMs, K. Yamamoto will consult R. Takahashi. |
2013 Nov. 26 |
009 |
2013 Nov. 19 |
T. Suzuki (?) |
Urgent! |
Control |
Check whether the thrust bearing can work at the cryogenic temperature. |
2013 Nov. 26 |
010 |
2013 Nov. 19 |
D. Chen (?) |
Urgent! |
Control |
About photodiode, check about out gas; check noises by 10-m long line; check whether the window of photodiode be removed. |
2013 Nov. 26 |