== KAGRA Commissioning status at DET meeting == * Date : 2022/08/29 === Overall schedule === * Overall schedule * 9/2 Closed the beam duct and connected the vacuum pumps PRM - SRM * 9/5 - 9/9 Closing the chamber with interferometer alignment * This week(?) pumping down started if all work are done * 9/20 - 9/22 OMC investigation for closing the chamber * 8/26 Acceptance check ~SRM * 9/13 - 9/16 Investigation of the ghost beam IFI and acceptance check