Size: 2411
Comment:
|
Size: 1628
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 1: | Line 1: |
* Overall schedule * End of July - End of August : Pumping down center area * Sep - Commissioning * X arm commissioning * Both IR and GR cavity lock keeping * IX : Cooling down the duct shield TM~250 K * EX : Cooling down the duct and two radiation shield TM~110K * Finesse and TM position by TCam are ongoing * TMSX optical table characterization : early July : After this, we can start ASC |
== KAGRA Commissioning status at DET meeting == * Date : 2022/06/20 === Overall schedule === * (In case of no trouble) * 6/20 - 6/24 Leak of End Y * 6/27 - Repair the leak point and start the pumping down * 6/20 - 7/1 Suspension commissioning Type-Bp * 7/4 - 7/8 Interferometer commissioning * 7/11 - 7/22 Suspension commissioning Type-B * 7/25 - 7/29 Acceptance check * 8/1 - Closing the center area * Mid size baffle installation * ISS installation * High power laser installation * (LVK information) * O4a will start March 2023 === Progress of commissioning === |
Line 11: | Line 26: |
* Pumping down started * EY has leak point, we will open the chamber soon * IR and GR lock succeeded! * Center area commissioning * Main IR * Table configuration : ongoing * IFO refl table [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9238|JGWDoc9238]] * POP (Pick of PR2) table [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9623|JGWDoc9623]] * POP forward QPD installed * Interesting channel for X arm IR lock : [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=14080|JGWDoc14080]] |
* IY leak test done * IY oplev windshield installed * Center area commissioning * MICH fringe detected ([[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21149|klog21149]]) |
Line 26: | Line 36: |
* PR3 : First contact (maybe) done | * PR3 : Installed |
Line 29: | Line 39: |
* Others * ITMX glitch from ADC * PR traverser limit switch install * Green related work === Interesting data === * X arm cavity * Both IR and GR * Y arm commissioning * Both IR and GR * Center area commissioning * Main IR |
|
Line 31: | Line 56: |
* Interesting point * Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) * Suspension commissioning : ongoing * PR's suspension middle of June - end of June (two weeks) * OMC installation : done * Some unexpected glitch : circuit? * Alignment : partially done : BS fluctuation large and SRM replacement * TF measurement : ongoing * High power laser * Accepted to install to KAGRA site * When exchange the laser source : Unknown * ISS (Intensity Stabilization System) installation : unknown * Must item before closing chamber * Interferometer commissioning * X and Y arm IR cavity lock check * Green laser system * Fiber noise cancelling check * ISC (Interferometer Sensing and Control, LSC and ASC) * Next : ALS DARM lock? * Action items before closing chamber : Will discuss tomorrow |
* Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) |
KAGRA Commissioning status at DET meeting
- Date : 2022/06/20
Overall schedule
- (In case of no trouble)
- 6/20 - 6/24 Leak of End Y
- 6/27 - Repair the leak point and start the pumping down
- 6/20 - 7/1 Suspension commissioning Type-Bp
- 7/4 - 7/8 Interferometer commissioning
- 7/11 - 7/22 Suspension commissioning Type-B
- 7/25 - 7/29 Acceptance check
- 8/1 - Closing the center area
- Mid size baffle installation
- ISS installation
- High power laser installation
- (LVK information)
- O4a will start March 2023
Progress of commissioning
- Y arm commissioning
- IY leak test done
- IY oplev windshield installed
- Center area commissioning
MICH fringe detected (klog21149)
- Mirror cleaning(first contact) and mid-size baffle installation
- PR2 : Installed
- SR2 : Installed
- BS : Installed
- PRM : Installed
- PR3 : Installed
- SR3 : Not yet
- SRM : Not yet (When replacement?)
- Others
- ITMX glitch from ADC
- PR traverser limit switch install
- Green related work
Interesting data
- X arm cavity
- Both IR and GR
- Y arm commissioning
- Both IR and GR
- Center area commissioning
- Main IR
- IMC (Input Mode Cleaner)
- ASC (Alignment Sensing and Control) done
- Long term stability check
- Beam power, beam position, oplev monitoring
- Glitch investigation
- Temperature dependence
- Relationship between PSL room
- With PEM channels
- (Hammering test?)