Line 16: | Line 16: |
* Mid size baffle installation * ISS installation * High power laser installation |
|
Line 17: | Line 21: |
* O4a will start March 2023 | * O4a will start March 2023 [[https://observing.docs.ligo.org/plan/|web]] |
Line 22: | Line 26: |
* IY leak test done * IY oplev windshield installed * |
* IY leak test done [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21135|klog#21135]] * IY oplev windshield installed [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21192|klog#21192]] * End Y : Start the leak (very slowly to avoid the dust.) * 1 week leaking, fixing early next week [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21191|klog#21191]] |
Line 26: | Line 31: |
* Center area commissioning * MICH fringe detected ([[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21149|klog#21149]]) * Mirror cleaning(first contact) and mid-size baffle installation * PR2 : Installed * SR2 : Installed [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=20205|cleaned]] * BS : Installed [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=20857|cleaned]] * PRM : Installed [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=20702|cleaned]] * PR3 : Installed [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21082|cleaned]] * SR3 : Not yet [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21212|cleaned]] * SRM : Not yet (When replacement?) [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21208|cleaned]] * Others * ITMX glitch from ADC [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=21185|klog#21185]] * PR traverser limit switch install * Green related work |
|
Line 33: | Line 52: |
* Pumping down started * EY has leak point, we will open the chamber soon * IR and GR lock succeeded! |
* Both IR and GR |
Line 38: | Line 56: |
* Table configuration : ongoing * IFO refl table [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9238|JGWDoc9238]] * POP (Pick of PR2) table [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=9623|JGWDoc9623]] * POP forward QPD installed * Interesting channel for X arm IR lock : [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=14080|JGWDoc14080]] * Mirror cleaning(first contact) and mid-size baffle installation * PR2 : Installed * SR2 : Installed * BS : Installed * PRM : Installed * PR3 : First contact (maybe) done * SR3 : Not yet * SRM : Not yet (When replacement?) |
|
Line 53: | Line 58: |
* Interesting point * Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) * Suspension commissioning : ongoing * PR's suspension middle of June - end of June (two weeks) * OMC installation : done * Some unexpected glitch : circuit? * Alignment : partially done : BS fluctuation large and SRM replacement * TF measurement : ongoing * High power laser * Accepted to install to KAGRA site * When exchange the laser source : Unknown * ISS (Intensity Stabilization System) installation : unknown * Must item before closing chamber * Interferometer commissioning * X and Y arm IR cavity lock check * Green laser system * Fiber noise cancelling check * ISC (Interferometer Sensing and Control, LSC and ASC) * Next : ALS DARM lock? * Action items before closing chamber : Will discuss tomorrow |
* Long term stability check * Beam power, beam position, oplev monitoring * Glitch investigation * Temperature dependence * Relationship between PSL room * With PEM channels * (Hammering test?) |
KAGRA Commissioning status at DET meeting
- Date : 2022/06/20
Overall schedule
- (In case of no trouble)
- 6/20 - 6/24 Leak of End Y
- 6/27 - Repair the leak point and start the pumping down
- 6/20 - 7/1 Suspension commissioning Type-Bp
- 7/4 - 7/8 Interferometer commissioning
- 7/11 - 7/22 Suspension commissioning Type-B
- 7/25 - 7/29 Acceptance check
- 8/1 - Closing the center area
- Mid size baffle installation
- ISS installation
- High power laser installation
- (LVK information)
O4a will start March 2023 web
Progress of commissioning
- Y arm commissioning
IY leak test done klog#21135
IY oplev windshield installed klog#21192
- End Y : Start the leak (very slowly to avoid the dust.)
1 week leaking, fixing early next week klog#21191
- Center area commissioning
MICH fringe detected (klog#21149)
- Mirror cleaning(first contact) and mid-size baffle installation
- Others
ITMX glitch from ADC klog#21185
- PR traverser limit switch install
- Green related work
Interesting data
- X arm cavity
- Both IR and GR
- Y arm commissioning
- Both IR and GR
- Center area commissioning
- Main IR
- IMC (Input Mode Cleaner)
- ASC (Alignment Sensing and Control) done
- Long term stability check
- Beam power, beam position, oplev monitoring
- Glitch investigation
- Temperature dependence
- Relationship between PSL room
- With PEM channels
- (Hammering test?)